Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
2 | 3 | 8.00 | 0.00 | HSIPIBZ8(659) |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
30 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 15,211.000 | |||
40800050 | TON | INCIDENTAL HOT-MIX ASPHALT SURFACING | Base items | 5.400 | |||
44000157 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL, 2" | Base items | 46.100 | |||
48203029 | SQ YD | HOT-MIX ASPHALT SHOULDERS, 8" | Base items | 33,730.000 | |||
64200108 | FOOT | SHOULDER RUMBLE STRIPS, 8 INCH | Base items | 75,847.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70100500 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701326 | Base items | 1.000 | |||
70103815 | CAL DA | TRAFFIC CONTROL SURVEILLANCE | Base items | 15.000 | |||
78009004 | FOOT | MODIFIED URETHANE PAVEMENT MARKING - LINE 4" | Base items | 168,380.000 | |||
X0800001 | SQ YD | SHOULDER REMOVAL (SPECIAL) | Base items | 33,730.000 | |||
Z0030850 | SQ FT | TEMPORARY INFORMATION SIGNING | Base items | 42.000 | |||
Z0048665 | L SUM | RAILROAD PROTECTIVE LIABILITY INSURANCE | Base items | 1.000 | |||