March 07, 2025 Letting 12:00 PM
03A-SO085

Bulletin Description

Expand Southeast Aircraft Parking Apron
Region District DBE % VBP % Federal Project #
5 9 7.00 0.00 N/A
County(s) IL Project # Airport Sponsor City
  • Jackson
MDH 5036 Southern Illinois Southern Illinois Airport Authority Murphysboro
Contract Specifics
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting.
49 Calendar Days
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 1 Answered ) Questions not accepted as of February 25, 2025 04:30 PM.

  • In the plans on sheet 4 and 5, it states that barricades are to be paid for under the AR150520 Mobilization pay item. However, on page 7 under the barricade notes, it states barricades should be in the cost of traffic maintenance. There is no pay item for traffic maintence. Please clearify how the barricades should be paid for.
    Barricades are to be paid for under the AR150520 Mobilization pay item. (02/14/2025)

Authorized Bidders

  • 5550 E. T. Simonds Construction Company
    1500 N Oakland Ave
    PO Box 2107
    Carbondale, IL 62902
    PO Box 2107
    Carbondale, IL 62902
    Phone: (618) 457-8191 Fax: (618) 549-0131 Email: jjones@etsimonds.com

  • 2262 Guinzy Construction,Inc.
    160 West Main St.
    Ashley, IL 62808
    P.O. Box 360
    Ashley, IL 62808
    Phone: (618) 485-2293 Fax: (618) 485-2552 Email: gcil@frontiernet.net

Non Bidders

  • 5306 Samron Midwest Contracting, Inc.
    (Pending Authorization)
    PO Box 1555
    Murphysboro, IL 62966
    Phone: (618) 687-5500 Fax: (618) 684-9341 Email: info@samron.com

  • 5526 Sierra Bravo Contractors, LLC
    (Pending Authorization)
    7038 Highway 154
    P.O. Box 130
    Sesser, IL 62884
    PO Box 130
    Sesser, IL 62884
    Phone: (618) 625-3456 Fax: (618) 625-6516 Email: engineering@sierrabravocontractors.com

Pay Item # UOM Description Type Quantity Unit Price
AR108108 FOOT 1/C #8 5 KV UG CABLE Base items 1,114.000
AR110012 FOOT 2" DIRECTIONAL BORE Base items 70.000
AR110202 FOOT 2" PVC DUCT, DIRECT BURY Base items 732.000
AR125565 EACH SPLICE CAN Base items 1.000
AR125961 EACH RELOCATE STAKE MOUNTED LIGHT Base items 5.000
AR125962 EACH RELOCATE BASE MOUNTED LIGHT Base items 2.000
AR125964 EACH RELOCATE TAXI GUIDANCE SIGN Base items 1.000
AR150520 L SUM MOBILIZATION Base items 1.000
AR150540 L SUM HAUL ROUTE Base items 1.000
AR152410 CU YD UNCLASSIFIED EXCAVATION Base items 1,295.000
AR155540 TON BY-PRODUCT LIME Base items 140.000
AR155616 SQ YD SOIL PROCESSING-16" Base items 3,988.000
AR156500 L SUM TEMPORARY EROSION CONTROL Base items 1.000
AR156530 ACRE TEMPORARY SEEDING Base items 0.800
AR209510 TON CRUSHED AGGREGATE BASE COURSE Base items 2,085.000
AR401613 TON BIT. SURF. CSE.-METHOD I, SUPERPAVE Base items 470.000
AR401900 SQ YD REMOVE BITUMINOUS PAVEMENT Base items 654.000
AR403613 TON BIT. BASE CSE.-METHOD I, SUPERPAVE Base items 950.000
AR602510 GALLON BITUMINOUS PRIME COAT Base items 1,975.000
AR603510 GALLON BITUMINOUS TACK COAT Base items 595.000
AR620520 SQ FT PAVEMENT MARKING-WATERBORNE Base items 350.000
AR620525 SQ FT PAVEMENT MARKING-BLACK BORDER Base items 350.000
AR701530 FOOT 30" RCP, CLASS IV Base items 234.000
AR705506 FOOT 6" PERFORATED UNDERDRAIN Base items 468.000
AR705630 EACH UNDERDRAIN INSPECTION HOLE Base items 1.000
AR705640 EACH UNDERDRAIN CLEANOUT Base items 2.000
AR705900 FOOT REMOVE UNDERDRAIN Base items 461.000
AR751411 EACH INLET-TYPE A Base items 1.000
AR751530 EACH MANHOLE Base items 1.000
AR751903 EACH REMOVE MANHOLE Base items 2.000
AR752900 EACH REMOVE END SECTION Base items 2.000
AR760947 EACH ADJUST WATER VALVE Base items 1.000
AR800476 L SUM REMOVE AIRFIELD LIGHTING Base items 1.000
AR800529 EACH RCP TEE STRUCTURE Base items 2.000
AR800918 SQ YD REMOVE RIPRAP Base items 45.000
AR800925 FOOT HDPE PIPE CULVERT Base items 90.000
AR901510 ACRE SEEDING Base items 0.800
AR908514 ACRE LIGHT-DUTY HYDRAULIC MULCH Base items 0.800
No More Pay Items