Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR108258 | FOOT | 2/C #8 5 KV UG CABLE IN UD | Base items | 4,204.000 | |||
AR108706 | FOOT | 1/C #6 COUNTERPOISE | Base items | 3,545.000 | |||
AR109200 | L SUM | INSTALL ELECTRICAL EQUIPMENT | Base items | 1.000 | |||
AR109302 | EACH | 4 KW REGULATOR, STYLE 2 | Base items | 1.000 | |||
AR109903 | EACH | REMOVE REGULATOR | Base items | 1.000 | |||
AR110014 | FOOT | 4" DIRECTIONAL BORE | Base items | 530.000 | |||
AR115610 | EACH | ELECTRICAL HANDHOLE | Base items | 1.000 | |||
AR125565 | EACH | SPLICE CAN | Base items | 1.000 | |||
AR125620 | EACH | ABBREVIATED PAPI (L-881 SYSTEM) | Base items | 2.000 | |||
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150530 | L SUM | TRAFFIC MAINTENANCE | Base items | 1.000 | |||
AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 32.000 | |||
AR800985 | EACH | FIELD LIGHTNING ARRESTOR | Base items | 6.000 | |||
AR901510 | ACRE | SEEDING | Base items | 0.100 | |||
AR905520 | CU YD | TOPSOILING (FROM OFF SITE) | Base items | 20.000 | |||
AR908510 | ACRE | MULCHING | Base items | 0.100 | |||
No More Pay Items |