001-46531
|
Executed
|
11/04/2019
|
|
|
4
|
7
|
Various
|
|
VARIOUS LENGTHS OF PAVEMENT MARKING REHABILITATION THROUGHOUT DISTRICT 7.
|
002-46535
|
Executed
|
11/04/2019
|
|
|
5
|
9
|
Various
|
|
REPAIRING VARIOUS WIDTHS OF THERMOPLASTIC, PREFORMED PLASTIC, AND URETHANE AND POLYUREA PAVEMENT MARKING LINES, LETTERS AND SYMBOLS AND THE REMOVAL OF EXISTING PAVEMENT MARKINGS ON A WORK ORDER BASIS THROUGHOUT DISTRICT 9.
|
003-60K72
|
Executed
|
10/17/2019
|
12 / 10 |
2 |
1
|
1
|
Cook
|
|
BRIDGE REHAB AND PAINTING ON WESTERN AVENUE OVER CAL-SAG CHANNEL (SN 016-0777).
|
004-61D65
|
Executed
|
10/22/2019
|
8 / 8 |
1 |
1
|
1
|
Lake
|
|
Reconstruct the intersection of Hart Road at US Route 14 in the Villages of Barrington and Barrington Hills.
|
005-61E69
|
Rejected
|
10/24/2019
|
7 / 7 |
2 |
1
|
1
|
DuPage
|
|
Landscaping and sign installation along the Elgin O'Hare Western Access Corridor at Lake Street (US 20), Roselle Road, Plum Grove Road and Rohlwing Road. Project is located in the villages of Roselle, Itasca and Hanover Park.
|
006-61F58
|
Executed
|
11/18/2019
|
2 / 1 |
|
1
|
1
|
McHenry
|
|
Reconstruct the intersection of Main Street at Crystal Lake Avenue in the city of Crystal Lake.
|
007-61F85
|
Executed
|
10/22/2019
|
4 / 4 |
|
1
|
1
|
DuPage
|
|
Streetscape to include sidewalk replacement, curb and gutter replacement, lighting improvements, landscaping, pavement imprinting and resurfacing. Project is located on Prospect Avenue from Ann Street to Burlington Avenue in the Village of Clarendon Hills.
|
008-61F93
|
Executed
|
10/25/2019
|
1 / 1 |
|
1
|
1
|
Cook
|
|
Resurfacing Broadway Avenue from Division Street to North Avenue in the Village of Melrose Park.
|
009-61F96
|
Executed
|
10/22/2019
|
|
1 |
1
|
1
|
Cook
|
|
Construction of Poplar Creek Trail from east of the intersection of Shoe Factory Road and the CN Railroad to west of the intersection of IL Route 59. Project is located within the Forest Preserve of Cook County Arthur Janura Forest Preserve in the Village of Hoffman Estates.
|
010-61F98
|
Executed
|
11/04/2019
|
4 / 4 |
1 |
1
|
1
|
McHenry
|
|
Sidewalk construction and culvert replacement on Main Street from Winn Road to West of Bilvin Street in the Village of Spring Grove.
|
011-61G00
|
Executed
|
10/21/2019
|
|
|
1
|
1
|
Lake
|
|
Reconstruction and resurfacing Rockland Road from east of the Des Plaines River bridge to St. Mary's Road, located in Libertyville Township, Lake County.
|
012-62A26
|
Deleted
|
08/12/2019
|
|
|
1
|
1
|
Cook
|
|
PAVEMENT WIDENING ON RAND ROAD TO PROVIDE FOR A NEW SOUTHBOUND RIGHT TURN LANE AT THE INTERSECTION OF RAND ROAD AND DUNDEE ROAD.
|
013-62G27
|
Deleted
|
08/16/2019
|
|
|
1
|
1
|
|
|
|
014-62G56
|
Executed
|
10/18/2019
|
|
1 |
1
|
1
|
McHenry
|
|
OVERLAY, NEW SHOULDERS AND MILLED RUMBLE STRIPS ON IL 31 FROM SHAMROCK LANE TO NORTH OF EDGEWOOD ROAD IN THE CITY OF MCHENRY AND VILLAGE OF PRAIRIE GROVE.
|
015-62H74
|
Executed
|
10/28/2019
|
1 / 1 |
1 |
1
|
1
|
Cook
|
|
PAVEMENT MARKING ROOSEVELT RD TO US 1 2/20 (95TH ST).
|
016-62H96
|
Deleted
|
08/16/2019
|
|
|
1
|
1
|
|
|
|
017-62J04
|
Executed
|
10/18/2019
|
|
1 |
1
|
1
|
Cook
|
|
1.9 MILES OF OVERLAY AND PEDESTRIAN RAMP IMPROVEMENTS ON IL 58 FROM BASSWOOD STREET TO I-290 / IL 53 IN THE VILLAGE OF SCHAUMBURG.
|
018-62J18
|
Executed
|
11/04/2019
|
1 / 1 |
|
1
|
1
|
Cook
|
|
SUBSTRUCTURE BRIDGE REPAIR OF SN 016-1094 CARRYING MILWAUKEE AVENUE OVER THE OHIO FEEDER IN THE CITY OF CHICAGO.
|
019-62J19
|
Executed
|
10/28/2019
|
|
1 |
1
|
1
|
Cook
|
|
11.9 MILES OF PAVEMENT MARKING REMOVAL, PAVEMENT MARKING INSTALLATION AND RAISED REFLECTIVE PAVEMENT MARKERS ON I-90/94 (DAN RYAN EXPRESSWAY) FROM ROOSEVELT ROAD TO US 12/20 (95TH STREET) WITHIN THE CITY OF CHICAGO.
|
020-62J61
|
Executed
|
10/30/2019
|
|
|
1
|
1
|
Various
|
|
HIGH TENSION CABLE BARRIER REPAIRS AT VARIOUS LOCATIONS ON VARIOUS EXPRESSWAY MEDIANS THROUGHOUT DISTRICT ONE.
|
021-64L16
|
Rejected
|
10/03/2019
|
1 / 1 |
1 |
2
|
2
|
Ogle
|
|
Pedestrian "ADA" ramps a various locations in Oregon and Polo.
|
022-64N78
|
Rejected
|
10/03/2019
|
2 / 2 |
1 |
2
|
2
|
Various
|
|
WASHING 12 BRIDGES AT VARIOUS LOCATIONS IN DISTRICT 2.
|
023-64N79
|
Executed
|
10/18/2019
|
|
|
2
|
2
|
Winnebago
|
|
WASHING 4 BRIDGES AT VARIOUS LOCATIONS.
|
024-64N81
|
Rejected
|
10/03/2019
|
|
|
2
|
2
|
Various
|
|
WASHING 19 BRIDGES AT VARIOUS LOCATIONS.
|
025-64N82
|
Executed
|
10/31/2019
|
|
|
2
|
2
|
Various
|
|
WASHING 6 BRIDGES OVER THE ROCK RIVER AT VARIOUS LOCATIONS.
|
026-64N83
|
Executed
|
10/24/2019
|
|
|
2
|
2
|
Rock Island
|
|
WASHING 2 BRIDGES OVER THE MISSISSIPPI RIVER.
|
027-64N85
|
Executed
|
10/31/2019
|
|
|
2
|
2
|
Various
|
|
WASHING 5 BRIDGES OVER THE ROCK RIVER.
|
028-64N86
|
Executed
|
10/31/2019
|
|
|
2
|
2
|
Various
|
|
WASHING 8 BRIDGES AT VARIOUS LOCATIONS.
|
029-66K34
|
Executed
|
10/18/2019
|
|
1 |
2
|
3
|
Iroquois
|
|
DRAINAGE REPAIRS 0.27 MI N OF CR 700 N ROAD.
|
030-68C57
|
Executed
|
10/17/2019
|
3 / 3 |
|
3
|
4
|
Peoria
|
|
SUPERSTRUCTURE REPLACEMENT TO SN 072-0073 CARRYING BELL SCHOOL RD OVER I-74 AND RESURFACE IL 78 FROM I-74 N 0.13 MI AND 0.2 MI S.
|
031-68C65
|
Executed
|
10/25/2019
|
4 / 4 |
2 |
3
|
4
|
Knox
|
|
CULVERT REPLACEMENTS ON IL 167 0.1 MI SE OF US 34/IL 167, AND 1.3 MI W OF TR 146.
|
032-68E16
|
Executed
|
10/22/2019
|
|
|
3
|
4
|
Peoria, Tazewell
|
|
CULVERT LINING ON VARIOUS ROUTES WITHIN PEORIA AND TAZEWELL COUNTIES.
|
033-68E27
|
Executed
|
10/18/2019
|
1 / 1 |
2 |
3
|
4
|
Tazewell
|
|
BRIDGE JOINT REPAIR, BRIDGE REPAIR TO SN 090-0127 CARRYING I-155 RAMP (NB) OVER BNSF AT IL 98 AND SN 090-0131 CARRYING MAIN ST (SB) OVER I-155 1.6 MI W OF IL 98 NEAR MORTON.
|
034-68E53
|
Executed
|
10/25/2019
|
|
|
3
|
4
|
Peoria, Tazewell
|
|
CONSTRUCTION, REPLACEMENT OR CROSSWALKS ALONG IL 29 (ADAMS and JEFFERSON ST) FROM HANCOCK ST TO WAYNE STREET IN PEORIA, IL 8 FROM CHERRY LANE TO MEADOWVIEW LN IN SUNNYLAND, IL 8 AT LEGION RD AND BUS 24 AT BONDURANT ST IN WASHINGTON.
|
035-64N84
|
Executed
|
10/24/2019
|
|
|
2
|
2
|
Various
|
|
WASHING 3 BRIDGES OVER THE MISSISSIPPI RIVER.
|
036-70B98
|
Deleted
|
08/12/2019
|
|
|
3
|
5
|
Champaign
|
|
BRIDGE REPLACEMENT.
|
037-72L38
|
Executed
|
10/22/2019
|
|
|
4
|
6
|
Morgan
|
|
PATCHING ON IL 267 FROM JUST NORTH OF I-72 TO JUST SOUTH OF I-72.
|
038-74880
|
Executed
|
10/17/2019
|
|
|
4
|
7
|
Various
|
|
REPAIR/REPLACEMENT OF DAMAGED STEEL PLATE BEAM GUARDRAIL THROUGHOUT DISTRICT 7.
|
039-74922
|
Executed
|
12/03/2019
|
|
|
4
|
7
|
Effingham
|
|
TREE REMOVAL AND SEEDING ALONG I-70 FROM MILE POST 98 TO MILE POST 105 EAST OF EFFINGHAM AND ALONG I-57 FROM THE I-70 / I-57 INTERCHANGE NORTH TO MILE POST 166 NORTHEAST OF EFFINGHAM.
|
040-76L31
|
Deleted
|
08/16/2019
|
|
|
5
|
8
|
|
|
|
041-76M37
|
Executed
|
10/25/2019
|
|
|
5
|
8
|
Madison, St. Clair
|
|
WELL TREATMENT AT VARIOUS LOCATIONS WITHIN DISTRICT 8.
|
042-76M38
|
Executed
|
10/24/2019
|
|
|
5
|
8
|
Various
|
|
REPAIR AND MAINTENANCE OF ELECTRICAL EQUIPMENT AT VARIOUS PUMP STATIONS THROUGHOUT DISTRICT 8.
|
043-76M39
|
Executed
|
10/24/2019
|
|
|
5
|
8
|
Calhoun
|
|
REPAIR AND MAINTENANCE OF THE ELECTRICAL EQUIPMENT AT THE JOE PAGE BRIDGE IN HARDIN.
|
044-78631
|
Executed
|
10/17/2019
|
3 / 3 |
3 |
5
|
9
|
Franklin
|
|
ADDITION OF A NEW LANE IN EACH DIRECTION, INSTALL A MEDIAN BARRIER AND UPGRADE GUARDRAIL ON A 3.2 MILE STRETCH OF I-57 FROM SOUTH OF THE COUNTRY CLUB ROAD OVERPASS TO MILE POST 66.
|
045-78736
|
Executed
|
10/22/2019
|
|
|
5
|
9
|
Johnson
|
|
4.3 MILES OF PATCHING ON NORTHBOUND I-57 FROM THE UNION COUNTY LINE TO THE WILLIAMSON COUNTY LINE.
|
046-78737
|
Executed
|
10/17/2019
|
|
|
5
|
9
|
Massac
|
|
13.2 MILES OF CENTERLINE RESURFACING ON EASTBOUND I-24 AT VARIOUS LOCATIONS FROM THE JOHNSON COUNTY LINE TO US 45.
|
047-78739
|
Executed
|
11/01/2019
|
|
|
5
|
9
|
Union
|
|
PAVED SHOULDER REMOVAL, PCC SHOULDERS, TIMBER CURB REMOVAL, CURB AND GUTTER, REMOVE AND REPLACE STONE RIP RAP TO REPAIR SLOPES ON US 51 AT SN 091-2002, 0.7 MILES NORTH OF ANNA.
|
048-85687
|
Rejected
|
10/03/2019
|
|
1 |
2
|
2
|
Winnebago
|
|
Remove guardrail and components, place HMA shoulders and install guardrail and traffic barrier terminals at various locations in Winnebago County.
|
049-89749
|
Executed
|
10/25/2019
|
2 / 2 |
|
3
|
4
|
Tazewell
|
|
Roadway reconstruction on Distillery Road from Front Street to IL 29, on Front Street from Distillery Road to Fayette Street and on Fayette Street from Front Street to IL 29 in the city of Pekin.
|
050-95860
|
Executed
|
10/23/2019
|
1 / 1 |
|
4
|
7
|
Wayne
|
|
Replace the bridge carrying TR 562 over King Creek, located 1.7 miles west of Golden Gate.
|
051-97692
|
Executed
|
11/18/2019
|
2 / 2 |
|
5
|
8
|
St. Clair
|
|
Reconstruction of Shiloh Station Road from South of Timberline Court to north of Johnson Road in the Village of Shiloh.
|
052-97707
|
Rejected
|
10/03/2019
|
|
|
5
|
8
|
Marion
|
|
Resurfacing, sidewalk replacement, curb and gutter on Hickory Street from 16th Street to Nolemen Street and on 16th Street from Hickory Street to Wabash Avenue in the city of Centrailia.
|
053-99631
|
Executed
|
10/17/2019
|
|
|
5
|
9
|
Williamson
|
|
Resurfacing Paulton Road from 0.3 miles north of Grant Brick Road to Toledo Road.
|
054-72J45
|
Deleted
|
08/07/2019
|
|
|
4
|
6
|
Hancock
|
|
Replacing the bridge carrying IL96 over Sheridan Creek, 0.9 miles south of Nauvoo (SN 034-0020).
|
055-78520
|
Deleted
|
08/07/2019
|
|
|
5
|
9
|
Jefferson
|
|
4.4 miles of safety shields, crown and superelevation correction, earthwork, drainage improvements and resurfacing on IL 37 from Casey Fork to Campground Road, just north of Bonnie.
|
056-76J16
|
Executed
|
10/25/2019
|
4 / 4 |
2 |
5
|
8
|
St. Clair
|
|
8.9 miles of resurfcing and ADA upgrades on IL 13/IL 15 from Roger's Drive in Freeburg to south of the Kaskasia River Bridge on IL 15.
|
057-76M16
|
Executed
|
11/13/2019
|
|
1 |
5
|
8
|
Madison
|
|
DECK WATERPROOFING, JOINT AND BEAM END REPAIRS ON SN 060-0226 CARRYING IL 140 OVER UPRR, 3.1 MILES WEST OF I-55 AND SN 060-0227 CARRYING IL 140 OVER NandWRR, 2.9 MILES WEST OF I-55.
|
058-62G42
|
Executed
|
10/28/2019
|
|
|
1
|
1
|
Cook
|
|
0.46 mile 3P resurfacing, pedestrian ramps, storm sewer repair, and drainage on Lawrence Ave from 471 ft east of Manheim Centerline to Rose St through Schiller Park, and east of Canfield Ave in Norridge.
|
059-68758
|
Executed
|
02/07/2020
|
|
1 |
3
|
4
|
Knox
|
|
Replacement of structure carrying IL 78 over kickapoo creek and replacement of a box culvert.
|
060-66K33
|
Withdrawn
|
08/28/2019
|
|
|
2
|
3
|
Livingston
|
|
AGGREGATE SHOULDERS ON I-55 EAST RAMPS TO IL 170.
|
061-70B53
|
Executed
|
10/31/2019
|
5 / 4 |
|
3
|
5
|
Champaign
|
|
1.533 miles of safety improvements on US 150/University Ave. from Wright St. to Cunningham Ave. in Urbana.
|
062-46530
|
Executed
|
10/21/2019
|
|
|
2
|
2
|
Various
|
|
Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and placing new raised pavement marker castings within the limits shown on the plans.
|
063-61F25
|
Executed
|
12/05/2019
|
3 / 3 |
1 |
1
|
1
|
Lake
|
|
Pavement reconstruction and the construction of a HMA pedestrian path next to Weiland Road from Aptakisic Road to Deerfield Parkway, and on Aptakistic Road from Joseph Court to Industrial Drive in the villages of Buffalo Grove and Lincolnshire.
|
064-87695
|
Rejected
|
10/03/2019
|
9 / 9 |
1 |
2
|
3
|
Grundy
|
|
Pavement widening and reconstruction of Ridge Road from a two-lane to a four-lane with bi-directional turn lane, includes bridge rehabilitation and the construction of a new bridge span to carry the Wisconsin Central Ltd. Railway over Ridge Road. Project runs from south of McEvilly Road to Minooka Road in the village of Minooka.
|
065-87711
|
Executed
|
10/15/2019
|
1 / 1 |
1 |
2
|
3
|
LaSalle
|
|
construction of the extension of Unytite Drive between Plank Road and Donlar Ave. in Peru.
|
066-87713
|
Executed
|
10/17/2019
|
|
1 |
2
|
3
|
LaSalle
|
|
Pavement widening and resurfacing on CH 15 from I-80 to IL 71.
|
067-99630
|
Executed
|
11/01/2019
|
|
|
5
|
9
|
Jackson
|
|
Reconstruction of Oakland Avenue from West Walnut Street to Chautauqua Street in the City of Carbondale.
|
068-46528
|
Rejected
|
10/03/2019
|
|
1 |
4
|
6
|
Logan
|
|
Installation of new automatic transfer switch at the storm water pump station on IL 121.
|
01A-TR009
|
Active
|
08/06/2019
|
|
1 |
2
|
2
|
Carroll
|
|
Airfield Pavement Maintenance including Crack Sealing and Re-Marking
|
02A-TR010
|
Executed
|
02/04/2020
|
|
|
2
|
2
|
Carroll
|
|
Install Precision Approach Path Indicator (PAPI) Units at Both Runway Ends
|
1LR-M1804
|
Active
|
08/14/2019
|
|
|
0
|
0
|
LaSalle; Livingston
|
Voluntary
|
Reclamation of the Old Sowerby Mine Group abandoned mine site by the Department of Natural Resources using federal Abandoned Mined Lands Funds
|