Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 7 | 5.00 | 0.00 | 77VP(507) |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
15 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200500 | CU YD | EARTH EXCAVATION (WIDENING) | Base items | 114.000 | |||
35501308 | SQ YD | HOT-MIX ASPHALT BASE COURSE, 6" | Base items | 686.000 | |||
40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 5,607.000 | |||
40602985 | TON | HOT-MIX ASPHALT BINDER COURSE, IL-9.5, N70 | Base items | 382.000 | |||
40604052 | TON | HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "C", N70 | Base items | 802.000 | |||
40800050 | TON | INCIDENTAL HOT-MIX ASPHALT SURFACING | Base items | 33.000 | |||
44000156 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL, 1 3/4" | Base items | 7,794.000 | |||
48101200 | TON | AGGREGATE SHOULDERS, TYPE B | Base items | 97.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70100460 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701306 | Base items | 1.000 | |||
78001110 | FOOT | PAINT PAVEMENT MARKING - LINE 4" | Base items | 7,575.000 | |||
X4060987 | SQ YD | PORTLAND CEMENT CONCRETE SURFACE REMOVAL - BUTT JOINT (SPECIAL) | Base items | 6.900 | |||
No More Pay Items |