Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
5 | 8 | 8.00 | 0.00 | 6ZQT(622) |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
40 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20100500 | ACRE | TREE REMOVAL, ACRES | Base items | 0.400 | |||
20200100 | CU YD | EARTH EXCAVATION | Base items | 80.000 | |||
20300100 | CU YD | CHANNEL EXCAVATION | Base items | 635.000 | |||
20400800 | CU YD | FURNISHED EXCAVATION | Base items | 315.000 | |||
40200800 | TON | AGGREGATE SURFACE COURSE, TYPE B | Base items | 184.000 | |||
50100100 | EACH | REMOVAL OF EXISTING STRUCTURES | Base items | 1.000 | |||
50300225 | CU YD | CONCRETE STRUCTURES | Base items | 45.400 | |||
50300280 | CU YD | CONCRETE ENCASEMENT | Base items | 29.800 | |||
50400405 | SQ FT | PRECAST PRESTRESSED CONCRETE DECK BEAMS (21" DEPTH) | Base items | 2,640.000 | |||
50800105 | POUND | REINFORCEMENT BARS | Base items | 6,730.000 | |||
50900205 | FOOT | STEEL RAILING, TYPE S1 | Base items | 225.000 | |||
51201600 | FOOT | FURNISHING STEEL PILES HP12X53 | Base items | 406.000 | |||
51201800 | FOOT | FURNISHING STEEL PILES HP14X73 | Base items | 460.000 | |||
51202305 | FOOT | DRIVING PILES | Base items | 866.000 | |||
51203600 | EACH | TEST PILE STEEL HP12X53 | Base items | 1.000 | |||
51203800 | EACH | TEST PILE STEEL HP14X73 | Base items | 1.000 | |||
51500100 | EACH | NAME PLATES | Base items | 1.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
72501000 | EACH | TERMINAL MARKER - DIRECT APPLIED | Base items | 4.000 | |||
X2070302 | TON | POROUS GRANULAR EMBANKMENT (SPECIAL) | Base items | 86.000 | |||
X2501000 | ACRE | SEEDING, CLASS 2 (SPECIAL) | Base items | 0.250 | |||
X2810808 | TON | STONE DUMPED RIPRAP, CLASS A4 (SPECIAL) | Base items | 328.000 | |||
X7010216 | L SUM | TRAFFIC CONTROL AND PROTECTION, (SPECIAL) | Base items | 1.000 | |||
No More Pay Items |