Home > Notice of Letting > Contract Detail

June 11, 2021 Letting 12:00 PM
177-74A51

Bulletin Description

18.7 miles of patching and A-2 surface treatment on various routes in Clay, Richland and Lawrence Counties.
Region District DBE % VBP % Federal Project #
4 7 0.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Various
  • VARIOUS
  • D7 SEAL COAT 2021-2
  • C-97-142-21
  • 7-52814-0000
Contract Specifics
35 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (1 Submitted / 1 Answered ) Questions not accepted as of June 01, 2021 04:30 PM.

  • You have 251 ton of prime coat and only 3200 sq yds of base prep. Shot at .35 this would be approximately 4.5 tons. Is this correct ? Thanks
    The project should be bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. (05/19/2021)

Authorized Bidders

  • 4270 Mt. Carmel Stabilization Group, Inc.
    1611 College Drive
    Mount Carmel, IL 62863
    PO Box 458
    Mt. Carmel, IL 62863
    Phone: (618) 262-5118 Fax: (618) 263-4084 Email: aireland@mtcsg.net
    $582,745.17

  • 1487 DMS Contracting, Inc.
    10243 Fuesser Road
    Mascoutah, IL 62258
    PO Box 122
    Mascoutah, IL 62258
    Phone: (618) 566-9114 Fax: (618) 566-3145 Email: estimating@dmscontracting.com
    $777,159.46

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
35800100 SQ YD PREPARATION OF BASE Base items 3,200.000
40300200 TON BITUMINOUS MATERIALS (PRIME COAT) Base items 251.000
40300405 TON POLYMERIZED BITUMINOUS MATERIALS (COVERS AND SEAL COATS) Base items 300.000
40300500 TON COVER COAT AGGREGATE Base items 2,523.000
40300600 TON SEAL COAT AGGREGATE Base items 2,523.000
67100100 L SUM MOBILIZATION Base items 1.000
70100450 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 Base items 1.000
70100460 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701306 Base items 1.000
70300100 FOOT SHORT TERM PAVEMENT MARKING Base items 4,963.000
78001110 FOOT PAINT PAVEMENT MARKING - LINE 4" Base items 55,836.000
X0300010 POUND BITUMINOUS MATERIALS (FOG SEAL) Base items 13,649.000
Z0005010 TON HOT-MIX ASPHALT FOR PATCHING POTHOLES (COLD MIX) Base items 50.000
No More Pay Items