| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 2 | 3 | 5.00 | 0.00 | 8AMN(810) |
| County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
|---|---|---|---|---|---|
|
|
|
|
|
|
| Contract Specifics |
|---|
| 30 Working Days |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| 40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 5,817.000 | |||
| 40602965 | TON | HOT-MIX ASPHALT BINDER COURSE, IL-9.5FG, N50 | Base items | 598.000 | |||
| 40604000 | TON | HOT-MIX ASPHALT SURFACE COURSE, IL-9.5FG, MIX "C", N50 | Base items | 598.000 | |||
| 42400200 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 5 INCH | Base items | 4,610.000 | |||
| 42400800 | SQ FT | DETECTABLE WARNINGS | Base items | 342.000 | |||
| 44000158 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL, 2 1/4" | Base items | 8,543.000 | |||
| 44000500 | FOOT | COMBINATION CURB AND GUTTER REMOVAL | Base items | 892.000 | |||
| 44000600 | SQ FT | SIDEWALK REMOVAL | Base items | 4,610.000 | |||
| 60255500 | EACH | MANHOLES TO BE ADJUSTED | Base items | 6.000 | |||
| 60266600 | EACH | VALVE BOXES TO BE ADJUSTED | Base items | 4.000 | |||
| 60603800 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 | Base items | 303.000 | |||
| 60604400 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.18 | Base items | 589.000 | |||
| 67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| 70102620 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701501 | Base items | 1.000 | |||
| 70102640 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701801 | Base items | 1.000 | |||
| 78000200 | FOOT | THERMOPLASTIC PAVEMENT MARKING - LINE 4" | Base items | 964.000 | |||
| 78000400 | FOOT | THERMOPLASTIC PAVEMENT MARKING - LINE 6" | Base items | 1,828.000 | |||
| 78000650 | FOOT | THERMOPLASTIC PAVEMENT MARKING - LINE 24" | Base items | 245.000 | |||
| No More Pay Items | |||||||