Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 4 | 0.00 | 0.00 | YKYJ(472) |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
20 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
40600295 | POUND | POLYMERIZED BITUMINOUS MATERIALS (TACK COAT) | Base items | 3,122.000 | |||
40603310 | TON | HOT-MIX ASPHALT SURFACE COURSE, MIX "C", N50 | Base items | 486.000 | |||
42000100 | SQ YD | PORTLAND CEMENT CONCRETE PAVEMENT 6" | Base items | 3.000 | |||
42400100 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 4 INCH | Base items | 890.000 | |||
42400800 | SQ FT | DETECTABLE WARNINGS | Base items | 130.000 | |||
44000100 | SQ YD | PAVEMENT REMOVAL | Base items | 3.000 | |||
44000157 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL, 2" | Base items | 4,336.000 | |||
44000500 | FOOT | COMBINATION CURB AND GUTTER REMOVAL | Base items | 57.000 | |||
44000600 | SQ FT | SIDEWALK REMOVAL | Base items | 834.000 | |||
60603900 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 (ABUTTING EXISTING PAVEMENT) | Base items | 57.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70102620 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701501 | Base items | 1.000 | |||
No More Pay Items |