Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 5 | 2.00 | 0.00 | 3170016037 |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
CMI 4877 | University of Illinois-Willard | University of Illinois | Savoy |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
27 Calendar Days |
Previously advertised on June 17, 2022 (Item 03A). |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AW125615 | EACH | PAPI (L-880 SYSTEM) | Base items | 2.000 | |||
AW125909 | EACH | REMOVE VASI | Base items | 8.000 | |||
AW150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AW150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AW154706 | SQ YD | CRUSHED AGG BASE COURSE - 6" | Base items | 300.000 | |||
AW156513 | SQ YD | SEPARATION FABRIC | Base items | 300.000 | |||
AW800223 | FOOT | PAPI 4 CIRCUIT, 2-1/C #8, 5KV CABLE, 1-#8 GND IN UNIT DUCT | Base items | 840.000 | |||
AW800224 | FOOT | PAPI 22 CIRCUIT, 3-#2, TYPE USE, 1-#8 GND IN UNIT DUCT | Base items | 1,175.000 | |||
AW800225 | FOOT | 1/C # 1/0 BARE COPPER GUARD WIRE WITH GROUND RODS | Base items | 2,015.000 | |||
AW901510 | ACRE | SEEDING | Base items | 0.400 | |||
AW908510 | ACRE | MULCHING | Base items | 0.400 | |||
AX150520 | L SUM | MOBILIZATION | Additive 1 | 1.000 | |||
AX152410 | CU YD | UNCLASSIFIED EXCAVATION | Additive 1 | 300.000 | |||
AX701524 | FOOT | 24" RCP, CLASS IV | Additive 1 | 66.000 | |||
AX751415 | EACH | INLET-SPECIAL | Additive 1 | 1.000 | |||
AX752424 | EACH | PRECAST REINFORCED CONC. FES 24" | Additive 1 | 2.000 | |||
No More Pay Items |