The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting.
75 Calendar Days
Previously advertised on June 11, 2021 (Item 04A).
No More Contract Specifics
AskSubscribe
Questions and Answers (4 Submitted / 4 Answered )
Questions not accepted as of January 11, 2022 04:30 PM.
Will the permanent markings be required to have 2 coats? Can you clarify what section 620-2.3.a is referring to since there is no 620-2.3.a listed in the specs for this project?
Please refer to specification section Item 620 in The State of Illinois Department of Transportation, Division of Aeronautics, Standard Specifications for Construction of Airports, adopted September 25, 2020 (latest revision), as well as the Special Provisions for this project. (01/12/2022)
Can a detail or description be provided for Item AR751952 Adjust Underdrain Structure? We need to know what existing material is being tied on to and/or if there are existing concrete colars etc to contend with.
A: According to record drawings, the underdrain structures appear to be a 6” diameter tube (PE or other material) with a typical cast iron frame and cover (similar to Neenah R-6013 or East Jordan 2790-6). The record drawings also indicate a concrete collar (18” dia.) surrounding the casting at grade. Please note that some of the existing structures were not able to be surveyed in the field, so we cannot confirm the condition of each structure. The intent of the structure adjustments is for the top of casting to be level with the proposed grade, with a concrete collar similar to existing conditions. (01/11/2022)
Are the RDR basecans B-size or D-size? Page 48 detail indicates both.
On Plan Sheet 48, the transformer base can that is to be located immediately adjacent to the proposed distance remaining sign shall be an L-867 Size B can, as noted on the details. The proposed L-867 Size D junction can that is also shown on the “Distance Remaining Sign Plan Detail” on this sheet is representing a junction can that is to be installed in line with the runway edge lights, and not adjacent to the distance remaining sign. These junction cans are also shown accordingly on the proposed electrical plan sheets. (12/21/2021)
Can you please confirm if there are any Runway Can Lights?
If so, please provide a total amount for Runway Grooving purposes
There are no existing or proposed runway can lights within the proposed paving/grooving limits for this project.
(12/21/2021)
Authorized Bidders
1034 Christ Bros. Asphalt, Inc.
820 s fritz st. P.O. Box 158 Lebanon, IL 62254
Phone: (618) 537-6174 Fax: (618) 537-6199 Email: No Record $4,796,846.79
3649 Charles E. Mahoney Co.
208 Service Street Swansea, IL 62226
Phone: (618) 235-3355 Fax: (618) 235-3356 Email: dale@mahoneyasphalt.com
Non Bidders
2308 Hank's Excavating & Landscaping, Inc. (Pending Authorization)
5825 West State Route 161 Belleville, IL 62223
Phone: (618) 398-5556 Fax: (618) 398-2729 Email: No Record
6537 Wissehr Electric, Inc.
5801 W State Route 161 Belleville, IL 62223
Phone: (618) 398-7575 Fax: (618) 398-7180 Email: jk@wissehr.com
Pay Item #
UOM
Description
Type
Quantity
Unit Price
AR108108
FOOT
1/C #8 5 KV UG CABLE
Base items
21,300.000
AR109200
L SUM
INSTALL ELECTRICAL EQUIPMENT
Base items
1.000
AR110012
FOOT
2" DIRECTIONAL BORE
Base items
1,290.000
AR110202
FOOT
2" PVC DUCT, DIRECT BURY
Base items
15,750.000
AR125400
EACH
REPLACE ISOLATION TRANSFORMER
Base items
5.000
AR125511
EACH
MIRL, BASE MOUNTED-LED
Base items
58.000
AR125512
EACH
MIRL, INPAVEMENT
Base items
2.000
AR125546
EACH
MI THRESHOLD LIGHT BASE MTD-LED
Base items
16.000
AR125561
EACH
RUNWAY DISTANCE REMAINING SIGN-LED
Base items
5.000
AR125565
EACH
SPLICE CAN
Base items
31.000
AR150510
L SUM
ENGINEER'S FIELD OFFICE
Base items
1.000
AR150520
L SUM
MOBILIZATION
Base items
1.000
AR150530
L SUM
TRAFFIC MAINTENANCE
Base items
1.000
AR401614
TON
BIT. SURF. CSE.-METHOD II, SUPERPAVE
Base items
14,885.000
AR401640
SQ YD
BITUMINOUS PAVEMENT GROOVING
Base items
68,627.000
AR401650
SQ YD
BITUMINOUS PAVEMENT MILLING
Base items
18,982.000
AR401900
SQ YD
REMOVE BITUMINOUS PAVEMENT
Base items
851.000
AR603510
GALLON
BITUMINOUS TACK COAT
Base items
25,886.000
AR620520
SQ FT
PAVEMENT MARKING-WATERBORNE
Base items
89,813.000
AR620525
SQ FT
PAVEMENT MARKING-BLACK BORDER
Base items
18,889.000
AR620590
SQ FT
TEMPORARY MARKING
Base items
89,813.000
AR751943
EACH
ADJUST MANHOLE
Base items
2.000
AR751952
EACH
ADJUST UNDERDRAIN STRUCTURE
Base items
21.000
AR800476
L SUM
REMOVE AIRFIELD LIGHTING
Base items
1.000
AR800552
EACH
CONCRETE MAINTENANCE PAD
Base items
2.000
AR800564
L SUM
CABLE & CCR TESTING & CALIBRATION
Base items
1.000
AR901510
ACRE
SEEDING
Base items
3.200
AR905530
SQ YD
TOPSOILING
Base items
15,573.000
AR908514
ACRE
LIGHT-DUTY HYDRAULIC MULCH
Base items
3.200
No More Pay Items