| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 4 | 7 | 6.00 | 0.00 | 317SBGPTBD |
| County(s) | IL Project # | Airport | Sponsor | City |
|---|---|---|---|---|
|
MTO 4752 | Coles County Memorial | Coles County Airport Authority | Mattoon |
| Contract Specifics |
|---|
| The time limit to award this item has been changed from 45 days to 60 days after the scheduled letting. |
| 115 Calendar Days |
| Note: This item is currently unfunded, but actively seeking discretionary funds. |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| AR108084 | FOOT | 1/C #4 XLP-USE | Base items | 6,551.000 | |||
| AR108108 | FOOT | 1/C #8 5 KV UG CABLE | Base items | 4,017.000 | |||
| AR108158 | FOOT | 1/C #8 5 KV UG CABLE IN UD | Base items | 4,244.000 | |||
| AR110013 | FOOT | 3" DIRECTIONAL BORE | Base items | 1,560.000 | |||
| AR110504 | FOOT | 4-WAY CONCRETE ENCASED DUCT | Base items | 310.000 | |||
| AR115610 | EACH | ELECTRICAL HANDHOLE | Base items | 2.000 | |||
| AR115710 | EACH | ELECTRICAL MANHOLE | Base items | 2.000 | |||
| AR125416 | EACH | MITL-BASE MOUNTED-LED | Base items | 9.000 | |||
| AR125442 | EACH | TAXI GUIDANCE SIGN, 2 CHARACTER | Base items | 1.000 | |||
| AR125443 | EACH | TAXI GUIDANCE SIGN, 3 CHARACTER | Base items | 1.000 | |||
| AR125446 | EACH | TAXI GUIDANCE SIGN, 6 CHARACTER | Base items | 1.000 | |||
| AR125932 | EACH | REPLACE SIGN PANEL | Base items | 58.000 | |||
| AR125943 | EACH | ADJUST INPAVEMENT LIGHT | Base items | 1.000 | |||
| AR125961 | EACH | RELOCATE STAKE MOUNTED LIGHT | Base items | 23.000 | |||
| AR125964 | EACH | RELOCATE TAXI GUIDANCE SIGN | Base items | 3.000 | |||
| AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
| AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| AR150540 | L SUM | HAUL ROUTE | Base items | 1.000 | |||
| AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 770.000 | |||
| AR152480 | SQ YD | SHOULDER ADJUSTMENT | Base items | 9,575.000 | |||
| AR156510 | FOOT | SILT FENCE | Base items | 688.000 | |||
| AR156513 | SQ YD | SEPARATION FABRIC | Base items | 1,710.000 | |||
| AR156530 | ACRE | TEMPORARY SEEDING | Base items | 3.000 | |||
| AR208540 | TON | OVERSIZE AGGREGATE | Base items | 600.000 | |||
| AR209606 | SQ YD | CRUSHED AGG. BASE COURSE - 6" | Base items | 1,710.000 | |||
| AR401614 | TON | BIT. SURF. CSE.-METHOD II, SUPERPAVE | Base items | 4,250.000 | |||
| AR401630 | EACH | BITUMINOUS SURFACE TEST SECTION | Base items | 1.000 | |||
| AR401640 | SQ YD | BITUMINOUS PAVEMENT GROOVING | Base items | 3,345.000 | |||
| AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 1,750.000 | |||
| AR403614 | TON | BIT. BASE CSE.-METHOD II, SUPERPAVE | Base items | 4,350.000 | |||
| AR403630 | EACH | BITUMINOUS BASE TEST SECTION | Base items | 1.000 | |||
| AR501120 | S.Y. | RUBBLIZE PAVEMENT | Base items | 31,935.000 | |||
| AR501550 | SQ YD | PCC PAVEMENT MILLING | Base items | 31,935.000 | |||
| AR501900 | SQ YD | REMOVE PCC PAVEMENT | Base items | 1,991.000 | |||
| AR501910 | SQ YD | REMOVE & REPLACE PCC PAVEMENT | Base items | 34.000 | |||
| AR602510 | GALLON | BITUMINOUS PRIME COAT | Base items | 577.000 | |||
| AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 5,500.000 | |||
| AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 10,538.000 | |||
| AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 8,830.000 | |||
| AR620900 | SQ FT | PAVEMENT MARKING REMOVAL | Base items | 351.000 | |||
| AR701512 | FOOT | 12" RCP, CLASS IV | Base items | 64.000 | |||
| AR705526 | FOOT | 6" PERFORATED UNDERDRAIN W/SOCK | Base items | 10,240.000 | |||
| AR705546 | FOOT | 6" NON PERFORATED UNDERDRAIN | Base items | 574.000 | |||
| AR705630 | EACH | UNDERDRAIN INSPECTION HOLE | Base items | 7.000 | |||
| AR705635 | EACH | UNDERDRAIN COLLECTION STRUCTURE | Base items | 7.000 | |||
| AR705640 | EACH | UNDERDRAIN CLEANOUT | Base items | 14.000 | |||
| AR705900 | FOOT | REMOVE UNDERDRAIN | Base items | 1,656.000 | |||
| AR705904 | EACH | REMOVE UNDERDRAIN CLEANOUT | Base items | 9.000 | |||
| AR751410 | EACH | INLET | Base items | 1.000 | |||
| AR751550 | EACH | MANHOLE 5' | Base items | 1.000 | |||
| AR751900 | EACH | REMOVE INLET | Base items | 1.000 | |||
| AR760708 | L.F. | 8" STEEL CASING | Base items | 108.000 | |||
| AR901510 | ACRE | SEEDING | Base items | 3.000 | |||
| AR905530 | SQ YD | TOPSOILING | Base items | 4,500.000 | |||
| AR908510 | ACRE | MULCHING | Base items | 3.000 | |||
| No More Pay Items | |||||||