Home > Notice of Letting > Contract Detail

April 29, 2022 Letting 12:00 PM
02A-SD061

Bulletin Description

Construct runup ramp and taxiway access from the airfield, including jet blast/ noise mitigation barrier
Region District DBE % VBP % Federal Project #
5 8 9.00 0.00 N/A
County(s) IL Project # Airport Sponsor City
  • St. Clair
CPS 4976 St. Louis Downtown Bi-State Development Agency Cahokia
Contract Specifics
A voluntary pre-bid meeting will be held on Tuesday, April 12, 2022 at 10:00 AM in the Saint Louis Downtown Airport at 6100 Archview Drive, Cahokia, IL 62206. Location Notes - Airport Administration Building Conference Room. Meeting Description - For Engineering information contact Barry Stolz, P.E. of Hanson Professional Services, Inc. at 314-942-5288.
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting.
149 Calendar Days
No More Contract Specifics

Ask Subscribe Questions and Answers (7 Submitted / 7 Answered ) Questions not accepted as of April 19, 2022 04:30 PM.

  • The material for the Oversize Aggregate pay item is supposed to be CA-1 per the Contract Specifications. Local quarries are not making CA-1 anymore and are requesting that RR-1 be allowed in place of the CA-1.
    This is acceptable and will be clarified by addendum. (04/19/2022)

  • Please supply a detail for the reinforcement panels in the non ferrous concrete showing bar sizes and spacing for fiberglass reinforcement. Will the dowel bars in the non ferrous concrete still be 1" x 18" ? Will they have to be smooth?
    On plan sheet 23, the Reinforcement Sheet Wire Fabric Detail is intended to reflect the minimum requirements for pavement reinforcement for the locations indicated on the jointing plan. In the non-ferrous concrete areas, the contractor shall provide non-ferrous materials in accordance with Reinforcing Note 7 that provides an equivalent reinforcement cross sectional area, which may include different bar sizes and/or spacing as needed to meet the minimum requirements. The non-ferrous dowel bars shall be the same size as the steel dowel bars and shall also be smooth, and shall have the same spacing as noted on the plans. (04/13/2022)

  • Will mulch be required for temporary seeding? If so, what type and at what rate?
    Mulch is not required for temporary seeding. (04/13/2022)

  • It is unclear what excavation and bedding is required under the box culvert. Please clarify.
    The detail sheet will be reissued by addendum to clarify the bedding. (04/13/2022)

  • Can the State provide electronic files, prior to bid, for existing and proposed contours?
    Refer to plan sheet 9, note 3 (inadvertently labeled as note 2) which states, “Following the project award, the Engineer can provide the relevant AutoCad and Civil 3D surface model files to the awarded Contractor upon request to assist with construction layout.” (04/13/2022)

  • The jointing plan on sheet 22 calls out different joints on the plan view that do not match there designation in the legend. Please clarify the plan view joint call out to match the legend.
    The plan sheet will be reissued by addendum to clarify the joint types. (04/13/2022)

  • Aerial imagery looks like there is an existing road that is to be improved. Will the newly installed / improved haul road be allowed to remain in place?
    The existing haul road is allowed to remain in place. If the contractor constructs additional length to the existing haul road, toward the north/work area, that new installation may be left in place up to a point that lines up with the runway holding position marking on Taxiway B7, which equates to approximately 350 feet of additional haul road that may remain at the conclusion of the project. Any newly installed haul road beyond that point (towards the north/work area) must be removed and restored to pre-construction conditions. (04/13/2022)

Authorized Bidders

  • 0338 Baxmeyer Construction, Inc.
    1034 Floraville Road
    Waterloo, IL 62298
    Phone: (618) 939-3000 Fax: (618) 939-4299 Email: estimator@baxmeyerconstruction.com
    Base $5,402,464.74
    Additive 1 $421,656.40
    Additive 2 $421,656.40
    Additive 3 $87,326.30

  • 1487 DMS Contracting, Inc.
    10243 Fuesser Road
    Mascoutah, IL 62258
    PO Box 122
    Mascoutah, IL 62258
    Phone: (618) 566-9114 Fax: (618) 566-3145 Email: estimating@dmscontracting.com

  • 2308 Hank's Excavating & Landscaping, Inc.
    5825 West State Route 161
    Belleville, IL 62223
    Phone: (618) 398-5556 Fax: (618) 398-2729 Email: No Record

  • 3108 Keller Construction, Inc.
    22 Illini Drive
    Glen Carbon, IL 62034
    Phone: (618) 656-0033 Fax: (618) 656-7134 Email: dan.walker@kellerconstruction.com

  • 4928 RCS Construction, Inc.
    960 E. Airline Drive
    East Alton, IL 62024
    Phone: (618) 254-3816 Fax: (618) 254-3841 Email: heather@rcs-construction.com

  • 5802 Stutz Excavating, Inc.
    3837 Fosterburg Road
    Alton, IL 62002
    Phone: (618) 259-2485 Fax: (618) 259-2465 Email: No Record

Non Bidders

  • 4135 Millstone Weber LLC
    (Pending Authorization)
    601 Fountain Lakes Blvd.
    St. Charles, MO 63301
    Phone: (636) 949-0038 Fax: (636) 949-3129 Email: bids@millstoneweber.com

Pay Item # UOM Description Type Quantity Unit Price
AR108108 FOOT 1/C #8 5 KV UG CABLE Base items 3,725.000
AR110012 FOOT 2" DIRECTIONAL BORE Base items 105.000
AR110202 FOOT 2" PVC DUCT, DIRECT BURY Base items 2,100.000
AR110501 FOOT 1-WAY CONC. ENCASED DUCT Base items 196.000
AR110502 FOOT 2-WAY CONCRETE ENCASED DUCT Base items 103.000
AR125416 EACH MITL-BASE MOUNTED-LED Base items 42.000
AR125443 EACH TAXI GUIDANCE SIGN, 3 CHARACTER Base items 2.000
AR125449 EACH TAXI GUIDANCE SIGN, 9 CHARACTER Base items 1.000
AR125565 EACH SPLICE CAN Base items 3.000
AR125902 EACH REMOVE BASE MOUNTED LIGHT Base items 1.000
AR150510 L SUM ENGINEER'S FIELD OFFICE Base items 1.000
AR150520 L SUM MOBILIZATION Base items 1.000
AR150540 L SUM HAUL ROUTE Base items 1.000
AR152410 CU YD UNCLASSIFIED EXCAVATION Base items 39,419.000
AR156500 L SUM TEMPORARY EROSION CONTROL Base items 1.000
AR156530 ACRE TEMPORARY SEEDING Base items 19.800
AR156531 SQ YD EROSION CONTROL BLANKET Base items 24,950.000
AR156540 SQ YD RIPRAP Base items 25.000
AR208540 TON OVERSIZE AGGREGATE Base items 22,330.000
AR209510 TON CRUSHED AGGREGATE BASE COURSE Base items 5,583.000
AR501512 SQ YD 12" PCC PAVEMENT Base items 10,664.000
AR501530 EACH PCC TEST BATCH Base items 1.000
AR620520 SQ FT PAVEMENT MARKING-WATERBORNE Base items 4,255.000
AR620525 SQ FT PAVEMENT MARKING-BLACK BORDER Base items 2,905.000
AR701174 FOOT PRECAST CONC. BOX CULVERT 7'X4' Base items 160.000
AR701524 FOOT 24" RCP, CLASS IV Base items 170.000
AR705943 EACH ADJUST UNDERDRAIN INSP. HOLE Base items 1.000
AR752424 EACH PRECAST REINFORCED CONC. FES 24" Base items 2.000
AR752648 EACH CONCRETE HEADWALL 48" Base items 2.000
AR800545 EACH MITL-BASE MOUNTED SIZE D Base items 6.000
AR800550 L SUM JET BLAST BARRIER/DEFLECTOR Base items 1.000
AR800551 SQ YD 12" PCC PAVEMENT, NON-FERROUS Base items 4,964.000
AR800564 L SUM CABLE & CCR TESTING & CALIBRATION Base items 1.000
AR901510 ACRE SEEDING Base items 19.800
AR908514 ACRE LIGHT-DUTY HYDRAULIC MULCH Base items 14.700
AS800550 L SUM JET BLAST BARRIER/DEFLECTOR Additive 1 1.000
AT800550 L SUM JET BLAST BARRIER/DEFLECTOR Additive 2 1.000
AU800527 L SUM APRON LIGHTING SYSTEM Additive 3 1.000
No More Pay Items