| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 5 | 9 | 0.00 | 0.00 | STPD5NP(319) |
| County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
|---|---|---|---|---|---|
|
|
|
|
|
|
| Contract Specifics |
|---|
| 20 Working Days |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| 40600990 | SQ YD | TEMPORARY RAMP | Base items | 253.000 | |||
| 40603315 | TON | HOT-MIX ASPHALT SURFACE COURSE, MIX "C", N70 | Base items | 2,871.000 | |||
| 40800029 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 14,130.000 | |||
| 44000157 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL, 2" | Base items | 31,400.000 | |||
| 48203100 | TON | HOT-MIX ASPHALT SHOULDERS | Base items | 723.000 | |||
| 64200108 | FOOT | SHOULDER RUMBLE STRIPS, 8 INCH | Base items | 18,076.000 | |||
| 67000400 | CAL MO | ENGINEER'S FIELD OFFICE, TYPE A | Base items | 1.000 | |||
| 67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| 70100460 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701306 | Base items | 1.000 | |||
| 70107025 | CAL DA | CHANGEABLE MESSAGE SIGN | Base items | 28.000 | |||
| 70300100 | FOOT | SHORT TERM PAVEMENT MARKING | Base items | 1,724.000 | |||
| 70300150 | SQ FT | SHORT TERM PAVEMENT MARKING REMOVAL | Base items | 575.000 | |||
| 70300220 | FOOT | TEMPORARY PAVEMENT MARKING - LINE 4" | Base items | 20,735.000 | |||
| 78009004 | FOOT | MODIFIED URETHANE PAVEMENT MARKING - LINE 4" | Base items | 20,735.000 | |||
| 78100100 | EACH | RAISED REFLECTIVE PAVEMENT MARKER | Base items | 119.000 | |||
| 78300200 | EACH | RAISED REFLECTIVE PAVEMENT MARKER REMOVAL | Base items | 119.000 | |||
| X7030005 | SQ FT | TEMPORARY PAVEMENT MARKING REMOVAL | Base items | 6,913.000 | |||
| Z0033700 | FOOT | LONGITUDINAL JOINT SEALANT | Base items | 9,482.000 | |||
| Z0034105 | TON | MATERIAL TRANSFER DEVICE | Base items | 2,871.000 | |||
| No More Pay Items | |||||||