Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 4 | 11.00 | 0.00 | 317SBGPTBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
MQB 4569 | Macomb Municipal | Macomb Airport Authority | Macomb |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
73 Calendar Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150530 | L SUM | TRAFFIC MAINTENANCE | Base items | 1.000 | |||
AR150540 | L SUM | HAUL ROUTE | Base items | 1.000 | |||
AR152480 | SQ YD | SHOULDER ADJUSTMENT | Base items | 11,100.000 | |||
AR156511 | EACH | DITCH CHECK | Base items | 3.000 | |||
AR201661 | FOOT | CLEAN & SEAL BITUMINOUS CRACKS | Base items | 3,000.000 | |||
AR201670 | SQ YD | CRACK CONTROL FABRIC | Base items | 560.000 | |||
AR401614 | TON | BIT. SURF. CSE.-METHOD II, SUPERPAVE | Base items | 2,880.000 | |||
AR401630 | EACH | BITUMINOUS SURFACE TEST SECTION | Base items | 1.000 | |||
AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 21,000.000 | |||
AR401660 | FOOT | SAW & SEAL BIT. JOINTS | Base items | 1,078.000 | |||
AR401915 | SQ YD | REM & REP BIT PAVEMENT - TYPE A | Base items | 112.000 | |||
AR401916 | SQ YD | REM & REP BIT PAVEMENT - TYPE B | Base items | 169.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 3,190.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 5,299.000 | |||
AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 9,554.000 | |||
AR620900 | SQ FT | PAVEMENT MARKING REMOVAL | Base items | 3,280.000 | |||
AR901510 | ACRE | SEEDING | Base items | 2.300 | |||
AR908510 | ACRE | MULCHING | Base items | 2.300 | |||
AS150530 | L SUM | TRAFFIC MAINTENANCE | Additive 1 | 1.000 | |||
AS152480 | SQ YD | SHOULDER ADJUSTMENT | Additive 1 | 1,297.000 | |||
AS201661 | FOOT | CLEAN & SEAL BITUMINOUS CRACKS | Additive 1 | 500.000 | |||
AS201670 | SQ YD | CRACK CONTROL FABRIC | Additive 1 | 190.000 | |||
AS401614 | TON | BIT. SURF. CSE.-METHOD II, SUPERPAVE | Additive 1 | 310.000 | |||
AS401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Additive 1 | 2,262.000 | |||
AS401660 | FOOT | SAW & SEAL BIT. JOINTS | Additive 1 | 140.000 | |||
AS401915 | SQ YD | REM & REP BIT PAVEMENT - TYPE A | Additive 1 | 48.000 | |||
AS401916 | SQ YD | REM & REP BIT PAVEMENT - TYPE B | Additive 1 | 48.000 | |||
AS603510 | GALLON | BITUMINOUS TACK COAT | Additive 1 | 350.000 | |||
AS901510 | ACRE | SEEDING | Additive 1 | 0.300 | |||
AS908510 | ACRE | MULCHING | Additive 1 | 0.300 | |||
No More Pay Items |