Home > Notice of Letting > Contract Detail

June 17, 2022 Letting 12:00 PM
009-62R32

Bulletin Description

(263.3-Ft) Improvement consist of bridge beam repairs for structure located on Touhy Avenue over Des Plaines River in the City of Park Ridge, Cook County.
Region District DBE % VBP % Federal Project #
1 1 4.00 0.00 NHPP0WKL(720)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Cook
  • FAP 341
  • TOUHY AVENUE
  • FA 525 21 STRUCTURE REHAB
  • C-91-127-22
  • 1-80889-0000
Contract Specifics
50 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (4 Submitted / 4 Answered ) Questions not accepted as of June 07, 2022 04:30 PM.

  • On the beam end repair, the diaphragm blocks horizontal flow of UHPC to the upper corner of the repair area as shown on Repair Detail R1, R9, R10 on Sheet S-7. Will IDOT accept a blocked out area from the end of the beam to the diaphragm?
    Size of the repair as shown on R1, R9 and R10 is achievable per details shown on Sheet S-7. Beam areas from the end of the beam to the diaphragm are most severely deteriorated and it is critical to incase them in UHPC. Therefore, it is our recommendation to execute the repair as shown on the drawings. (06/13/2022)

  • Can the blocking supporting the diaphragms at beam end repair 1 be removed to allow for formwork to be installed, will it be required to be reinstalled after the beam repairs have been completed?
    The existing wood blocking can be removed and doesn't need to be reinstalled after the repairs are completed. (06/07/2022)

  • The schedule requirements specified in the special provisions for Ultra High-Performance Concrete require a submittal of 30 calendar days prior to trial batch and mockup, which must be completed 45 days prior to construction would only allow 2 working days for final construction. Please confirm the contract duration of 50 working days will not begin until after approval of UHPC Trial Batch and Mockup.
    The contract duration of 50 working days will not begin until after approval of UHPC Trial Batch and Mockup. (06/07/2022)

  • Beam end repair details shows both core holes on the same side of the diaphragms, has the designer confirmed the UHPC will flow to the side of diaphragm opposite of the core and fill up to the bottom of the bridge deck?
    The UHPC repair for the end diaphragm only requires the UHPC material to be applied on one side of the diaphragm. See details on sheet S-8. (06/07/2022)

Authorized Bidders

  • 4677 Path Construction Company, Inc.
    125 E. Algonquin Road
    Arlington Heights, IL 60005
    Phone: (847) 997-9147 Fax: (847) 398-7101 Email: PSowa@pathcc.com
    $458,553.25

  • 0103 Alliance Contractors, Inc.
    1166 Lake Avenue
    Woodstock, IL 60098
    Phone: (815) 338-5900 Fax: (815) 338-9109 Email: estimating@alliancecontractors.com

  • 1604 Era-Valdivia Contractors, Inc.
    11909 S. Avenue O
    Chicago, IL 60617
    Phone: (773) 721-9350 Fax: (773) 721-8027 Email: estimating@eravaldivia.com

  • 3208 Kiewit Infrastructure Co.
    Two Pierce Place
    Suite 1600
    Itasca, IL 60143
    Phone: (773) 458-1250 Fax: (773) 458-1342 Email: Estimating.GLAO@kiewit.com
    $631,779.44

  • 3505 Lorig Construction Company
    250 East Touhy Avenue
    Des Plaines, IL 60018
    Phone: (847) 298-0360 Fax: (847) 298-2689 Email: estimating@lorigconstruction.com
    $646,050.65

  • 3574 MYS, Incorporated
    12416 S. Harlem Ave
    Palos Heights, IL 60463
    Phone: (708) 448-0983 Fax: (708) 448-8098 Email: tyelnick@mysincorporated.com

  • 6272 Vixen Construction, Inc.
    7600 W. 79th Street
    Bridgeview, IL 60455
    Phone: (708) 728-1950 Fax: (708) 728-1960 Email: No Record

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
50500505 EACH STUD SHEAR CONNECTORS Base items 741.000
64300240 EACH IMPACT ATTENUATORS (FULLY REDIRECTIVE, NARROW), TEST LEVEL 2 Base items 2.000
67100100 L SUM MOBILIZATION Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 70.000
70300150 SQ FT SHORT TERM PAVEMENT MARKING REMOVAL Base items 2,815.000
70307120 FOOT TEMPORARY PAVEMENT MARKING - LINE 4" - TYPE IV TAPE Base items 6,659.000
70307130 FOOT TEMPORARY PAVEMENT MARKING - LINE 6" - TYPE IV TAPE Base items 1,194.000
70400100 FOOT TEMPORARY CONCRETE BARRIER Base items 1,100.000
70400200 FOOT RELOCATE TEMPORARY CONCRETE BARRIER Base items 1,100.000
70600322 EACH IMPACT ATTENUATORS, RELOCATE (FULLY REDIRECTIVE, NARROW), TEST LEVEL 2 Base items 2.000
78000100 SQ FT THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 77.000
78000200 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 4" Base items 9,071.000
78000400 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 6" Base items 527.000
78000600 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 12" Base items 615.000
78000650 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 24" Base items 95.000
78009004 FOOT MODIFIED URETHANE PAVEMENT MARKING - LINE 4" Base items 1,548.000
78009012 FOOT MODIFIED URETHANE PAVEMENT MARKING - LINE 12" Base items 85.000
78100300 EACH REPLACEMENT REFLECTOR Base items 220.000
78200011 EACH BARRIER WALL REFLECTORS, TYPE C Base items 124.000
78300200 EACH RAISED REFLECTIVE PAVEMENT MARKER REMOVAL Base items 220.000
78300202 SQ FT PAVEMENT MARKING REMOVAL - WATER BLASTING Base items 1,259.000
X0100030 CU FT ULTRA - HIGH PERFORMANCE CONCRETE FOR STEEL BEAM END ENCASEMENT Base items 117.400
X0325222 GALLON WEED CONTROL, BASAL TREATMENT Base items 1.000
X6700407 CAL MO ENGINEER'S FIELD OFFICE, TYPE A (D1) Base items 12.000
X7010216 L SUM TRAFFIC CONTROL AND PROTECTION, (SPECIAL) Base items 1.000
Z0030850 SQ FT TEMPORARY INFORMATION SIGNING Base items 43.000
Z0073510 EACH TEMPORARY TRAFFIC SIGNAL TIMING Base items 2.000
Z0076600 HOUR TRAINEES Base items 500.000 $0.80
Z0076604 HOUR TRAINEES TRAINING PROGRAM GRADUATE Base items 500.000 $15.00
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.