Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 7 | 5.00 | 0.00 | 317SBGPTBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
MTO 4923 | Coles County Memorial | Coles County Airport Authority | Mattoon |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
78 Calendar Days |
This project is currently unfunded but actively seeking discretionary funds |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150530 | L SUM | TRAFFIC MAINTENANCE | Base items | 1.000 | |||
AR150540 | L SUM | HAUL ROUTE | Base items | 1.000 | |||
AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 300.000 | |||
AR152480 | SQ YD | SHOULDER ADJUSTMENT | Base items | 9,989.000 | |||
AR156510 | FOOT | SILT FENCE | Base items | 616.000 | |||
AR201661 | FOOT | CLEAN & SEAL BITUMINOUS CRACKS | Base items | 9,513.000 | |||
AR201670 | SQ YD | CRACK CONTROL FABRIC | Base items | 1,950.000 | |||
AR209510 | TON | CRUSHED AGGREGATE BASE COURSE | Base items | 150.000 | |||
AR401614 | TON | BIT. SURF. CSE.-METHOD II, SUPERPAVE | Base items | 6,396.000 | |||
AR401630 | EACH | BITUMINOUS SURFACE TEST SECTION | Base items | 1.000 | |||
AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 27,305.000 | |||
AR401660 | FOOT | SAW & SEAL BIT. JOINTS | Base items | 745.000 | |||
AR401663 | FOOT | LONGITUDINAL JOINT SEALANT | Base items | 14,071.000 | |||
AR401915 | SQ YD | REM & REP BIT PAVEMENT - TYPE A | Base items | 779.000 | |||
AR401916 | SQ YD | REM & REP BIT PAVEMENT - TYPE B | Base items | 519.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 5,181.000 | |||
AR605540 | FOOT | CLEAN & SEAL JOINTS | Base items | 258.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 7,253.000 | |||
AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 7,467.000 | |||
AR620555 | SQ FT | PREFORMED THERMOPLASTIC | Base items | 701.000 | |||
AR620900 | SQ FT | PAVEMENT MARKING REMOVAL | Base items | 1,261.000 | |||
AR901510 | ACRE | SEEDING | Base items | 2.100 | |||
AR908510 | ACRE | MULCHING | Base items | 2.100 | |||
No More Pay Items |