Home > Notice of Letting > Contract Detail

September 17, 2021 Letting 12:00 PM
011-62M86

Bulletin Description

This contract is for annual maintenance of electrical systems including the Signal Systems, Lighting Systems, Pump Station Systems, Surveilliance System and other Electrical Systems, many subsystems and components, mechanical system and including buildings, structures and grounds located withing District 1.
Region District DBE % VBP % Federal Project #
1 1 0.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Various
  • VARIOUS
  • 2020-213-I
  • C-91-008-21
  • N/A
Contract Specifics
A mandatory pre-bid meeting will be held on Thursday, August 26, 2021 at 10:30 AM in the District 1 at 201 West Center Court, Schaumburg, IL 60196. Location Notes - Lower Level Classroom. Meeting Description - For additional information about the mandatory meeting, refer to Article 1.4 on page 23 of the published Special Provisions. The pre-bid meeting is mandatory for all potential prime contractors interested in bidding. Registered subcontractors and certified disadvantaged business enterprise subcontractors are encouraged to attend. The meeting will begin at 10:30 AM at which time, after a final call for everyone to sign in, the sign-in sheets will be copied. Attendees who show up after the presentation is underway will not be allowed to sign-in thereby not being considered in attendance. Failure on the prime contractor's part to attend will cause the contractor's request for authorization to bid to be denied.
Completion Date: December 31, 2022
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 2 Answered ) Questions not accepted as of September 07, 2021 04:30 PM.

  • With the supply chain delay issues and material costs skyrocketing, rather than the contractor pricing all that risk into routine maintenance items would the Department entertain a cost escalation adjustment at least yearly?
    The project should be bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. (09/07/2021)

  • Current EMC (62F52) states: When structural problems are found on towers or monopoles, including towers at the Rodenburg and Woodstock Maintenance Yard location, the Engineer shall be immediately notified. Structural problems or deficiencies are not the responsibility of the Contractor. This language is not found in 62M86, is it the departments intention to have any structural problems or deficiencies on towers or monopoles to be the responsibility of the contractor under Routine Maintenance?
    Contract language should have been "When structural problems are thought to be present on towers or monopoles, including towers at the Rodenburg and Woodstock Maintenance Yard locations, the Engineer shall be immediately notified." The Contractor is not responsible for structural problems or deficiencies, as stated in Article 7.22 - "The Department hires a structural engineering company to perform structural inspections of Light Towers; and to examine the lowering system equipment. The Contractor shall be provided the yearly schedule of the structural inspection company when known, but which may be on short notice as IDOT District 1 does not dictate the schedule." (09/07/2021)

Authorized Bidders

  • 3948 Meade Inc.
    625 Willowbrook Center Pkwy
    Wilowbrook, IL 60527
    Phone: (708) 588-2500 Fax: (708) 588-2501 Email: infraestimating@meade100.com

Non Bidders

  • 0080 Aldridge Electric, Inc.
    (Pending Authorization)
    844 E. Rockland Rd.
    Libertyville, IL 60048
    Phone: (847) 680-5200 Fax: (847) 680-5233 Email: hcullen@aldridgegroup.com

  • 0733 John Burns Construction Company
    (Pending Authorization)
    999 Oakmont Plaza Drive, Suite 400
    Westmont, IL 60559
    Phone: (708) 638-7642 Fax: (708) 326-3499 Email: lmartinez@jbcco.com

Pay Item # UOM Description Type Quantity Unit Price
X0320990 L SUM DISTRICT ONE - ELECTRICAL MAINTENANCE Base items 1.000
No More Pay Items