Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
1 | 1 | 0.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
Small Business Initiative (Bid Bond is not required) |
30 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20100110 | UNIT | TREE REMOVAL (6 TO 15 UNITS DIAMETER) | Base items | 108.000 | |||
20101000 | FOOT | TEMPORARY FENCE | Base items | 1,118.500 | |||
21101625 | SQ YD | TOPSOIL FURNISH AND PLACE, 6" | Base items | 2,163.000 | |||
25000200 | ACRE | SEEDING, CLASS 2 | Base items | 0.450 | |||
25000400 | POUND | NITROGEN FERTILIZER NUTRIENT | Base items | 41.000 | |||
25000600 | POUND | POTASSIUM FERTILIZER NUTRIENT | Base items | 41.000 | |||
25100105 | ACRE | MULCH, METHOD 1 | Base items | 0.450 | |||
28000400 | FOOT | PERIMETER EROSION BARRIER | Base items | 928.000 | |||
44000200 | SQ YD | DRIVEWAY PAVEMENT REMOVAL | Base items | 1,443.000 | |||
44000500 | FOOT | COMBINATION CURB AND GUTTER REMOVAL | Base items | 490.000 | |||
44000600 | SQ FT | SIDEWALK REMOVAL | Base items | 65.000 | |||
55100400 | FOOT | STORM SEWER REMOVAL 10" | Base items | 93.000 | |||
55100500 | FOOT | STORM SEWER REMOVAL 12" | Base items | 118.000 | |||
60500050 | EACH | REMOVING CATCH BASINS | Base items | 3.000 | |||
60603800 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 | Base items | 80.000 | |||
66900200 | CU YD | NON-SPECIAL WASTE DISPOSAL | Base items | 35.000 | |||
66900530 | EACH | SOIL DISPOSAL ANALYSIS | Base items | 1.000 | |||
66901001 | L SUM | REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN | Base items | 1.000 | |||
66901002 | CAL DA | ON-SITE MONITORING OF REGULATED SUBSTANCES | Base items | 3.000 | |||
66901003 | L SUM | REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT | Base items | 1.000 | |||
67000400 | CAL MO | ENGINEER'S FIELD OFFICE, TYPE A | Base items | 6.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70102620 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701501 | Base items | 1.000 | |||
70102625 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701606 | Base items | 1.000 | |||
X0326694 | CU YD | PLUG EXISTING STORM SEWERS | Base items | 1.000 | |||
X0840000 | FOOT | SANITARY SEWER REMOVAL 8" | Base items | 55.000 | |||
X2010400 | UNIT | STUMP REMOVAL ONLY | Base items | 120.000 | |||
X5010205 | EACH | REMOVAL OF EXISTING STRUCTURE (SPECIAL) | Base items | 1.000 | |||
X5620124 | FOOT | WATER SERVICE LINE REMOVAL | Base items | 75.000 | |||
X6026054 | EACH | SANITARY MANHOLES TO BE REMOVED | Base items | 2.000 | |||
Z0007601 | L SUM | BUILDING REMOVAL NO. 1 | Base items | 1.000 | |||
Z0007602 | L SUM | BUILDING REMOVAL NO. 2 | Base items | 1.000 | |||
Z0015500 | L SUM | DEBRIS REMOVAL | Base items | 1.000 | |||
Z0030850 | SQ FT | TEMPORARY INFORMATION SIGNING | Base items | 102.800 | |||
Z0064800 | UNIT | SELECTIVE CLEARING | Base items | 33.000 | |||
No More Pay Items |