                                               ILLINOIS DEPARTMENT OF TRANSPORTATION                                      PAGE:    1
 10/18/21  11:36:38                   U N I T  P R I C E   T A B U L A T I O N   O F   B I D S
 LETTING DATE: 04/23/2021  LETTING TYPE: SCHEDULED                                 CONTRACT NUMBER: 93736  LETTING ITEM NUMBER: 103
 RESPONSIBLE DISTRICT: 06                                                                                  BIDS LOCKED: Y
 SECTION: 19-00056-07-PV                           COUNTY: MENARD                                          ESTIMATE:
 STATE JOB NUMBER:   C-96-012-20                   MUNICIPALITY:
 PROJECT NUMBER: 9VY4-469 /   /
                                                      --------------------------
                                                      SUMMARY OF CONTRACTOR BIDS
                                                      --------------------------

                                                             "AS READ"          SUMMATION    SUMMATION OF                       NBR
 BIDR                     CONTR        COMB  ITEM  CONTR      BIDDER            OF BIDDER     CALCULATED   LOW   BIDR CALC      BLANK
 NBR   BIDDER NAME        GROUP  COMB  GRP   NBR   GROUP      TOTAL PRICE       EXTENSIONS    EXTENSIONS   BID   EXTENSION DIFF BIDS


 0673  P. H. Broughton & Sons, Inc. and Perry Broughton
       Trucking and Excavating, Inc.
                          NO ALT                            2,301,298.38     2,301,298.38   2,301,298.38

 2825  Illinois Valley Paving, a div of UCM, Inc.
                          NO ALT                            2,166,704.97 *   2,166,704.97   2,166,704.97    *

 **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT =      45
                                                       ----------------------
                                                       DETAIL CONTRACTOR BIDS
                                                       ----------------------

    ITEM NBR  ITEM DESCRIPTION                                    UNIT OF     UNIT        BIDDER         CALCULATED  BIDR CALC
 BIDR NBR  BIDDER NAME                                  QUANTITY  MEASURE     PRICE       EXTENSION      EXTENSION   EXTENSION DIFF


    X0327112  STUMP REMOVAL ACRES                           .750     ACRE
 2825      Illinois Valley Paving, a div of UCM, Inc.                  37,888.9200       28,416.69       28,416.69
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                               67,825.0000       50,868.75       50,868.75

    X0327301  RELOCATE EX MAILBOX                         10.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                     997.9100        9,979.10        9,979.10
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  418.0300        4,180.30        4,180.30

    X2501000  SEEDING CL  2 SPL                           10.500     ACRE
 2825      Illinois Valley Paving, a div of UCM, Inc.                   2,157.7500       22,656.38       22,656.38
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                2,586.8200       27,161.61       27,161.61

    X6061460  PAVED DITCH SPEC                            22.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                     220.5400        4,851.88        4,851.88
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  230.8400        5,078.48        5,078.48

    X7010216  TRAF CONT & PROT SPL                         1.000    L SUM
 2825      Illinois Valley Paving, a div of UCM, Inc.                  17,403.4400       17,403.44       17,403.44
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                               15,510.1900       15,510.19       15,510.19

    Z0013798  CONSTRUCTION LAYOUT                          1.000    L SUM
 2825      Illinois Valley Paving, a div of UCM, Inc.                   9,569.2100        9,569.21        9,569.21
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                               13,148.7700       13,148.77       13,148.77

    Z0023602  GRAN CULVERT BACKFILL                    1,824.000    CU YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                     100.8000      183,859.20      183,859.20
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   76.1500      138,897.60      138,897.60

    Z0041500  PLUG EX CULVERTS                             2.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                   1,766.6200        3,533.24        3,533.24
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                4,187.0000        8,374.00        8,374.00

    Z0076600  TRAINEES                                 1,000.000     HOUR
 2825      Illinois Valley Paving, a div of UCM, Inc.                       0.8000          800.00          800.00
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    0.8000          800.00          800.00

    Z0076604  TRAINEES TPG                             1,000.000     HOUR
 2825      Illinois Valley Paving, a div of UCM, Inc.                      15.0000       15,000.00       15,000.00
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   15.0000       15,000.00       15,000.00

    20200100  EARTH EXCAVATION                         6,596.000    CU YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                      11.7000       77,173.20       77,173.20
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   12.5700       82,911.72       82,911.72

    20400800  FURNISHED EXCAVATION                    23,631.000    CU YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                      23.6700      559,345.77      559,345.77
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   41.5400      981,631.74      981,631.74

    28000250  TEMP EROS CONTR SEED                     1,050.000    POUND
 2825      Illinois Valley Paving, a div of UCM, Inc.                       5.4100        5,680.50        5,680.50
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    4.8000        5,040.00        5,040.00

    28000305  TEMP DITCH CHECKS                          325.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      81.9000       26,617.50       26,617.50
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   11.8700        3,857.75        3,857.75

    28000400  PERIMETER EROS BAR                       5,985.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                       3.9500       23,640.75       23,640.75
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    5.0300       30,104.55       30,104.55

    28000500  INLET & PIPE PROTECT                        12.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                     435.8900        5,230.68        5,230.68
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  300.0000        3,600.00        3,600.00

    28300400  AGGREGATE DITCH                          1,245.000      TON
 2825      Illinois Valley Paving, a div of UCM, Inc.                      93.2000      116,034.00      116,034.00
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   48.6800       60,606.60       60,606.60

    35100100  AGG BASE CSE A                             348.000      TON
 2825      Illinois Valley Paving, a div of UCM, Inc.                      59.5500       20,723.40       20,723.40
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   45.6700       15,893.16       15,893.16

    35600700  HMA BC WID  6                            3,225.000    SQ YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                      32.5400      104,941.50      104,941.50
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   37.6800      121,518.00      121,518.00

    40600275  BIT MATLS PR CT                          1,164.000    POUND
 2825      Illinois Valley Paving, a div of UCM, Inc.                       1.9400        2,258.16        2,258.16
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    0.6700          779.88          779.88

    40600290  BIT MATLS TACK CT                        9,371.000    POUND
 2825      Illinois Valley Paving, a div of UCM, Inc.                       1.1400       10,682.94       10,682.94
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    0.5500        5,154.05        5,154.05

    40600982  HMA SURF REM BUTT JT                       305.000    SQ YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                      43.8300       13,368.15       13,368.15
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   21.6500        6,603.25        6,603.25

    40603080  HMA BC IL-19.0  N50                      2,430.000      TON
 2825      Illinois Valley Paving, a div of UCM, Inc.                      89.5100      217,509.30      217,509.30
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   89.6600      217,873.80      217,873.80

    40604050  HMA SC IL-9.5 C N50                      1,712.000      TON
 2825      Illinois Valley Paving, a div of UCM, Inc.                     103.6400      177,431.68      177,431.68
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   94.5800      161,920.96      161,920.96

    44000100  PAVEMENT REM                             1,083.000    SQ YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                      51.8800       56,186.04       56,186.04
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    9.9400       10,765.02       10,765.02

    48100100  AGGREGATE SHLDS A                        3,375.000      TON
 2825      Illinois Valley Paving, a div of UCM, Inc.                      30.4500      102,768.75      102,768.75
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   31.1300      105,063.75      105,063.75

    50105220  PIPE CULVERT REMOV                         562.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      45.6800       25,672.16       25,672.16
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   15.7900        8,873.98        8,873.98

    542A0229  P CUL CL A 1    24                          32.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                     100.2600        3,208.32        3,208.32
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   90.1400        2,884.48        2,884.48

    542A1909  P CUL CL A 3    24                         388.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                     210.1700       81,545.96       81,545.96
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   81.8200       31,746.16       31,746.16

    542A3391  P CUL CL A 5    36                         204.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                     209.6400       42,766.56       42,766.56
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  132.5000       27,030.00       27,030.00

    542D0220  P CUL CL D 1    15                         108.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      32.5100        3,511.08        3,511.08
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   80.1100        8,651.88        8,651.88

    542D0223  P CUL CL D 1    18                          38.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      41.9700        1,594.86        1,594.86
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   98.7600        3,752.88        3,752.88

    542D0229  P CUL CL D 1    24                          44.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      54.3700        2,392.28        2,392.28
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  116.5000        5,126.00        5,126.00

    542D1060  P CUL CL D 2    15                          30.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      19.9400          598.20          598.20
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   80.1100        2,403.30        2,403.30

    542D1063  P CUL CL D 2    18                          56.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                      42.7200        2,392.32        2,392.32
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   98.7600        5,530.56        5,530.56

    54213669  PRC FLAR END SEC 24                          8.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                   1,636.0900       13,088.72       13,088.72
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                1,300.0000       10,400.00       10,400.00

    54213681  PRC FLAR END SEC 36                          2.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                   1,903.5400        3,807.08        3,807.08
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                2,306.3300        4,612.66        4,612.66

    54262715  METAL FL END SEC 15"                         8.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                     585.2400        4,681.92        4,681.92
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  430.1000        3,440.80        3,440.80

    54262718  METAL FL END SEC 18"                         4.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                     585.2400        2,340.96        2,340.96
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  688.2800        2,753.12        2,753.12

    54262724  METAL FL END SEC 24"                         2.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                     797.3800        1,594.76        1,594.76
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                1,029.5400        2,059.08        2,059.08

    59300100  CONTR LOW-STRENG MATL                      290.000    CU YD
 2825      Illinois Valley Paving, a div of UCM, Inc.                     199.3900       57,823.10       57,823.10
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  182.8300       53,020.70       53,020.70

    66600105  FUR ERECT ROW MARKERS                       40.000     EACH
 2825      Illinois Valley Paving, a div of UCM, Inc.                     275.7000       11,028.00       11,028.00
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                  201.4100        8,056.40        8,056.40

    67100100  MOBILIZATION                                 1.000    L SUM
 2825      Illinois Valley Paving, a div of UCM, Inc.                  78,649.0300       78,649.03       78,649.03
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                               14,045.2500       14,045.25       14,045.25

    70107025  CHANGEABLE MESSAGE SN                      150.000   CAL DA
 2825      Illinois Valley Paving, a div of UCM, Inc.                      65.6300        9,844.50        9,844.50
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                   67.0900       10,063.50       10,063.50

    78001110  PAINT PVT MK LINE  4                    15,530.000     FOOT
 2825      Illinois Valley Paving, a div of UCM, Inc.                       0.2900        4,503.70        4,503.70
 0673      P. H. Broughton & Sons, Inc. and Perry Broughton
           Trucking and Excavating, Inc.                                    0.2900        4,503.70        4,503.70