001-46922
|
Executed
|
10/14/2020
|
2 / 2 |
1 |
5
|
9
|
Massac
|
|
HMA resurfacing of roadway and parking areas, striping of parking areas, sign replacement, aggregate resurfacing of camp sites, HMA paving of existing camp sites, parking lot and sidewalk construction and site lighting at Fort Massac State Park (IDNR) in Metropolis.
|
002-60P14
|
Executed
|
10/19/2020
|
4 / 4 |
|
1
|
1
|
Cook
|
|
(1.22 miles) The 3 signalized intersections include: IL 72 at Oakton St. (W Jct), IL 72 at IL 83 Busse Rd and IL 72 east of IL 83 (E Jct). IL 72 and IL 83 intersection is approx. 1000 FT south of I-90.
|
003-60V06
|
Executed
|
10/19/2020
|
1 / 1 |
1 |
1
|
1
|
Lake
|
|
Precast concrete pavement and class B concrete patches along IL 83, approximately 419 ft E of the center line of N Buffalo Grove Rd and approximately 29833 ft NE to US 45.
|
004-60Y21
|
Executed
|
10/19/2020
|
4 / 4 |
1 |
1
|
1
|
Cook
|
|
(0.30-miles) Intersection Reconstruction (traffic signal modernization, addition of turn lanes) at the intersection of IL 19 (Irving Park Road) and Scott Street and at Judd Avenue.
|
005-62B66
|
Deleted
|
08/13/2020
|
|
|
1
|
1
|
Lake
|
|
Decommissioning of existing Pump Station 37 located in the bridge abutment (SN 049-0131), new pump station in the northeast quadrant of the US 41 and IL 176 intersection, new outfall pipe to the Skokie River.
|
006-62H79
|
Executed
|
10/14/2020
|
12 / 12 |
|
1
|
1
|
Will
|
|
Traffic Signal modernization and Traffic Signal Retroreflective Backplate Installation at various locations in the City of Joliet.
|
007-62K28
|
Executed
|
10/19/2020
|
1 / 1 |
|
1
|
1
|
Will
|
|
(0.53 Mile) Traffic signal installation, median reconstruction, new sidewalk installation, and ADA and drainage improvement at the intersection of IL 59 and Champion Road.
|
008-62K94
|
Executed
|
11/05/2020
|
1 / 1 |
1 |
1
|
1
|
Lake
|
|
Weigh Station Repairs (remove and replace scales, steel beam support and deck platform, repairs to the pit walls and replacement of approach pavements. Location: Northbound Wasdworth Weigh Station in Wadsworth, Lake County.
|
009-62L01
|
Executed
|
11/26/2020
|
|
|
1
|
1
|
Cook
|
|
(0.528 Mile) standard overlay with ADA ramp improvement from 26th St to 31st St in the Village of Riverside, in Riverside Township.
|
010-62L14
|
Executed
|
11/05/2020
|
|
|
1
|
1
|
Cook
|
|
(0.92 Mile) Standard Overlay, ADA Improvement, Located on Meacham Road from south of Emerson Ave to ILL 62 (Algonquin Road).
|
011-62L96
|
Executed
|
12/07/2020
|
|
|
1
|
1
|
Cook
|
|
(3.05 Miles) Crack and Joint Sealing Improvements, Location: FAP 350; IL 50/US 41 (Skokie Blvd.) from North of Golf Rd to Touhy Ave.
|
012-62L97
|
Executed
|
12/07/2020
|
|
|
1
|
1
|
Cook
|
|
(2.60 Miles) Crack and joint sealing, includes pavement marking re-striping. Located from Will-Cook Road to Southwest Highway.
|
013-62M66
|
Executed
|
11/26/2020
|
|
|
1
|
1
|
McHenry
|
|
Building Demolition at 3 locations. Location No. 1: 2103 N. Woodlawn Parkway; Location No. 2 2107 N. Woodlawn Parkway; Locaton No. 3 W. side of IL 31, approximately 2,250-ft N. of McCullom Lake.
|
014-62M72
|
Executed
|
11/23/2020
|
13 / 13 |
|
1
|
1
|
Will
|
|
Traffic Signal Modernization and Traffic Signal Retroreflective Backplate Installation at various locations in the City of Joliet.
|
015-64A08
|
Executed
|
10/15/2020
|
13 / 12 |
3 |
2
|
2
|
Winnebago
|
|
Bridge Replacement under 20th St 0. 7 Mi E of IL 251 in Rockford.
|
016-64P20
|
Executed
|
10/28/2020
|
|
|
2
|
2
|
Various
|
|
Washing six bridges over the Rock River at various locations.
|
017-64P21
|
Executed
|
11/26/2020
|
|
|
2
|
2
|
Rock Island
|
|
Washing SN 081-0011 over the Mississippi.
|
018-64P23
|
Executed
|
10/28/2020
|
1 / 1 |
|
2
|
2
|
Various
|
|
Washing five bridges over the Rock River at various locations.
|
019-66L09
|
Executed
|
10/19/2020
|
|
|
2
|
3
|
Bureau
|
|
This work is located on FAS Route 1279 (US 34) carrying US 34 adjacent to a concrete Box culvert, Structure No. 006-2569, Station 428+72 in Bureau County. This project consists of installing a 36" ERS concrete Pipe culvert adjacent to the box culvert.
|
020-66L11
|
Executed
|
10/14/2020
|
1 / 1 |
|
2
|
3
|
Bureau, DeKalb
|
|
This work is located at various intersections on US 6 in Bureau County and IL 38 in DeKalb County. This work consists of the removal and replacement of traffic signal "Controller Cabinets."
|
021-66L27
|
Executed
|
10/14/2020
|
2 / 2 |
|
2
|
3
|
LaSalle
|
|
This work is located at Structure No. 050-2539 carrying IL 170 over Armstrong Run. Approximately 3.86 miles south of US 6 in LaSalle County. This project consists of removing and replacing two wing walls of the structure.
|
022-68741
|
Executed
|
10/14/2020
|
|
1 |
3
|
4
|
Putnam
|
|
This project is 550 feet long and consists of superstructure replacement on S.N. 078-0032, which carries IL Route 71 over Coffee Creek, 5.1 miles west of IL Route 89 in Putnam County.
|
023-68E79
|
Executed
|
10/15/2020
|
5 / 5 |
2 |
3
|
4
|
Tazewell
|
|
Bridge rehabilitation, joint replacement, and deck repairs to SN 090-0114 over the Illinois River at Pekin.
|
024-68F57
|
Executed
|
10/19/2020
|
6 / 6 |
1 |
3
|
4
|
Various
|
|
Upgrade guardrail terminal end sections, Texas Turndowns, along various routes throughout the district in various counties.
|
025-70602
|
Executed
|
10/15/2020
|
2 / 2 |
2 |
3
|
5
|
Champaign
|
|
0.1 miles, bridge superstructure, Copper Slough W of Duncan Rd.
|
026-70E94
|
Executed
|
10/15/2020
|
|
|
3
|
5
|
McLean
|
|
Bridge Joint Repair of S.N. 057-0223 carrying Raab Rd. over 1-55.
|
027-72M37
|
Executed
|
10/14/2020
|
|
|
4
|
6
|
Scott
|
|
Bridge superstructure repairs on SN 086-0037 and SN 086-0038 carrying I-72 over IL 100.
|
028-72M39
|
Executed
|
10/21/2020
|
|
|
4
|
6
|
Scott
|
|
Patching on I-72 from the abandoned BandN Railroad to the Morgan County line.
|
029-72M40
|
Executed
|
10/19/2020
|
|
|
4
|
6
|
Montgomery
|
|
Patching on I-55 at the Coalfield Rest Area.
|
030-74A29
|
Executed
|
10/19/2020
|
1 / 1 |
|
4
|
7
|
Clark
|
|
7 miles of patching on I-70 from mile post 130 to 137.
|
031-76H84
|
Executed
|
10/20/2020
|
7 / 7 |
1 |
5
|
8
|
Madison
|
|
2.5 miles of standard overlay resurfacing along I-70/270 from I-55 to 2.5 miles east of the I-55/70/270 interchange and the ramps at the I-55/70/270 interchange and 4.7 miles of ultra-thin bonded wearing course from 0.4 miles east of IL 159 to 0.3 miles north of I-270.
|
032-78590
|
Rejected
|
10/07/2020
|
|
|
5
|
9
|
Saline
|
|
16.3 miles of tree pruning along IL 34 and US 45.
|
033-78799
|
Executed
|
10/15/2020
|
|
|
5
|
9
|
Massac, Pulaski
|
|
9 miles of HMA surface removal, HMA surface course, pavement patching and ADA curb ramp improvements on IL 169 from IL 37 to US 45.
|
034-78822
|
Executed
|
10/14/2020
|
|
|
5
|
9
|
Williamson
|
|
High friction surface treatment on the northbound I-57 entrance Ramp A and Ramp A-R; Ramp A begins at IL 13 and continues to The Hill Avenue overpass; Ramp A-R begins at IL 13 and ends where it merges into Ramp A.
|
035-46547
|
Executed
|
11/26/2020
|
|
|
2
|
2
|
Various
|
|
This work shall consist of removing existing guardrail delineators and installing new guardrail delineators within the limits specified on each individual work order.
|
036-46551
|
Executed
|
10/14/2020
|
|
|
2
|
2
|
Various
|
|
This work shall consist of placing various widths of modified urethane and thermoplastic pavement marking lines, letters and symbols within the limits specified on each individual work order.
|
037-46559
|
Executed
|
10/14/2020
|
|
|
4
|
7
|
Various
|
|
Various types of pavement marking rehabilitation throughout District 7.
|
038-62B65
|
Executed
|
11/05/2020
|
13 / 12 |
4 |
1
|
1
|
Lake
|
Voluntary
|
US 41 @ Deerpath Rd-PS#38. New pump station 38 in the SW quadrant of Deerpath Rd. @ Ahwahnee Ln., decommissioning existing pump station at bridge abutement (SN 049-0033). 2 detention ponds in Lake Forest golf course, 2 new ret. walls, resurfacing, drainage repairs (0.49 miles)
|
039-72L22
|
Executed
|
10/20/2020
|
|
|
4
|
6
|
Logan, Montgomery
|
|
Removal and replacement of high mast light towers on I-55 at the Litchfield and Elkhart interchanges.
|
040-74364
|
Deleted
|
08/12/2020
|
|
|
4
|
7
|
Cumberland
|
|
Removal and replacement of SN 018-0028 carrying IL 121 over Long Point Branch Creek, 1.3 miles east of Montrose Road. , Removal and replacement of SN 018-0028 carrying IL 121 over Long Point Branch Creek, 1.3 miles east of Montrose Road.
|
041-76L20
|
Executed
|
10/28/2020
|
2 / 2 |
2 |
5
|
8
|
Greene, Jersey
|
|
5.7 miles of standard overlay resurfacing on US 67 from 0.1 miles north of Township Road 285 to 0.6 miles south of Tolman Road.
|
042-76M61
|
Executed
|
10/15/2020
|
|
1 |
5
|
8
|
Various
|
|
Repair and maintenance of electrical equipment at pump stations in various locations within District 8.
|
043-76M62
|
Executed
|
10/15/2020
|
|
|
5
|
8
|
Calhoun
|
|
Repair and maintenance of electrical equipment on the Joe Page Bridge in Hardin (SN 031-0001).
|
044-76M78
|
Active
|
08/05/2020
|
|
|
5
|
8
|
Madison, St. Clair
|
|
Chemical treatment of deep wells at various locations in East St. Louis.
|
045-76N15
|
Executed
|
10/19/2020
|
2 / 2 |
|
5
|
8
|
Madison
|
|
Bridge joint repairs and HMA overlay with bridge repairs on SN 060-0278 and 060-0279 on IL 255 over the Cahokia Diversion Canal.
|
046-46454
|
Executed
|
10/19/2020
|
|
1 |
5
|
9
|
Jefferson, Johnson
|
|
Repairing or replacing damaged or deteriorated overhead sign structures, overhead sign structure components and supports at various locations in Jefferson and Johnson Counties.
|
047-60Y23
|
Executed
|
10/19/2020
|
2 / 2 |
1 |
1
|
1
|
Cook
|
|
(0.32- mile) Right turn lane, traffic signal modernization, and ADA improvement. Location: Willow Road, from 646-ft west of the centerline of the centerline of Pfingsten Road to 524- ft east of the centerline of Pfingsten Road in the Villages of Glenview and Northbrook, Northfield Township.
|
048-61F90
|
Executed
|
10/21/2020
|
1 / 1 |
1 |
1
|
1
|
Lake
|
|
Sidewalk construction at various locations in Lake Villa.
|
049-61G15
|
Executed
|
10/15/2020
|
|
|
1
|
1
|
Cook
|
|
Streetscape improvements on IL 21 from Jonquil Terrace to Howard Street, in the Village of Niles.
|
050-61G48
|
Executed
|
11/26/2020
|
|
|
1
|
1
|
Cook
|
|
Remove and replace sidewalks, curb and gutter, and driveways on 13th Street, from 23rd Avenue to 17th Avenue, and on 15th Street from 21st Avenue to 19th Avenue in Broadview.
|
051-64P22
|
Executed
|
11/26/2020
|
|
|
2
|
2
|
Various
|
|
Washing three bridges (SN-s 008-0052, 081-9905, 098-6003) over the Mississippi River.
|
052-85684
|
Executed
|
11/02/2020
|
|
|
2
|
2
|
Rock Island
|
|
Construction of a shared-use path adjacent to Avenue of the Cities, from Hospital Road to Greenview Memorial Gardens in the City of Silvs.
|
053-85696
|
Executed
|
10/15/2020
|
|
|
2
|
2
|
Rock Island
|
|
Remove and replace guardrail and terminals at various locations in Rock Island County.
|
054-89754
|
Withdrawn
|
09/12/2020
|
6 / 3 |
1 |
3
|
4
|
Woodford
|
|
Remove and replace guardrail and terminals at various locations in Woodford County. , Remove and replace guardrail and terminals at various locations in Woodford County.
|
055-93749
|
Executed
|
11/26/2020
|
4 / 2 |
|
4
|
6
|
Sangamon
|
|
Milling and resurfacing for a three lane section with bike lane and new traffic signals on Walnut Street from South Grand Avenue to Monroe Street in Springfield.
|
056-93750
|
Rejected
|
11/05/2020
|
|
|
4
|
6
|
Christian
|
|
Replace the existing pedestrian bridge with a prefabricated pedestrian superstructure located on Lincoln Prairie Trail over Flat Branch, adjacent to IL 29 between Pana and Taylorville.
|
057-97726
|
Active
|
08/06/2020
|
5 / 4 |
1 |
5
|
8
|
Greene
|
|
Sidewalk construction at various locations in the city of Carrollton.
|
058-97737
|
Executed
|
12/17/2020
|
|
|
5
|
8
|
Monroe
|
|
Resurfacing, curb and gutter, sidewalks, HMA multi-use path, storm sewers and pavement markings, on Quarry Road from Ghent Road to Palmer Creek Drive in Columbia.
|
059-62L13
|
Executed
|
10/14/2020
|
|
|
1
|
1
|
Lake
|
|
(0.5 Mile) Designed Overlay, ADA Improvements, Located on Barrington Road from ILL 176 (Liberty St) to US 12 (Rand Rd) in the Village of Wauconda in Lake County.
|
060-64L14
|
Executed
|
10/14/2020
|
5 / 5 |
2 |
2
|
2
|
Winnebago
|
|
Intersection Reconstruction, Standard Overlay, Traffic Signal Modernization and MUP from Mid America Dr to Buckley Dr in Rockford.
|
061-66K51
|
Executed
|
10/19/2020
|
1 / 1 |
|
2
|
3
|
Iroquois
|
|
3P milling and resurfacing from IL 54 in Onarga to North St in Buckley according to TAMP designed overlay policy. Other work includes culvert work, grading and shaping ditches, stabilization, shoulder stone, pavement marking, and raised reflectors.
|
062-66L07
|
Executed
|
10/14/2020
|
|
|
2
|
3
|
LaSalle
|
|
Repairing scour/erosion damage under both abutments by filling the existing void under the footings with a self-consolidating concrete and installing a riprap slope at SN 050-0059 carrying FAP 607 (US 52) over Mission Creek approximately 0.3 mi W of IL 71 in LaSalle County.
|
1LR-M1904
|
Deleted
|
08/14/2020
|
|
|
0
|
0
|
Vermilion
|
Voluntary
|
|
2LR-M1907
|
Deleted
|
08/14/2020
|
|
|
0
|
0
|
Saline
|
Voluntary
|
|
3LR-M2001
|
Deleted
|
08/14/2020
|
|
|
0
|
0
|
Williamson
|
Voluntary
|
|