001-62M56
|
Executed
|
12/27/2022
|
1 / 1 |
|
1
|
1
|
Cook
|
|
(2,738-Ft) The improvement consists of bridge deck scarification, overlay and expansion joint replacement on a bridge carrying US Route 14 over Des Plaines River located in the City of Des Plaines in Cook County.
|
002-62N31
|
Executed
|
01/03/2023
|
4 / 4 |
|
1
|
1
|
Various
|
|
(3.04-Mile) Temp pavement construction, median and shoulder rehab, ditch grading, temp drainage improvements, traffic staging, earthwork, erosion control, construction layout, pavement markings, temp lighting, and landscaping on I-80 from E of Ridge Road to E of River Road in Villages of Minooka and Shorewood and Troy Township.
|
003-62N51
|
Executed
|
12/20/2022
|
2 / 2 |
1 |
1
|
1
|
Will
|
|
(1.52-Mile) SMART Overlay and curb ramps (ADA) improvements on IL 7 from West of Canal Street to East of Read Street. This project is located in City of Lockport in Will County.
|
004-62N53
|
Executed
|
12/27/2022
|
1 / 1 |
1 |
1
|
1
|
Cook
|
|
(4200 feet) This is a SMART overlay project on IL Route 21 from Glenview Rd to North of Kennicott Ln. It is located in Village of Glenview in Cook County.
|
005-62N67
|
Executed
|
12/20/2022
|
1 / 1 |
1 |
1
|
1
|
Lake
|
|
(2.62-Mile); Smart Overlay and ADA Improvements on IL 83 from S of Hook Drive to Lake Avenue, located in the Villages of Round Lake Beach and Lake Villa in Lake County.
|
006-62R30
|
Executed
|
01/03/2023
|
6 / 6 |
|
1
|
1
|
Will
|
|
(491-Ft) Complete structure replacement of the bridge carrying Wheeler Avenue over Interstate 80 (1-80), pavement reconstruction, guardrail replacement, etc. Located 5.4 miles east of 1-55, in Joliet Township.
|
007-62T90
|
Executed
|
01/03/2023
|
|
|
1
|
1
|
Various
|
|
The work to be completed under this contract consists of installing guardrail at new locations and repairing existing damaged guardrail and traffic barrier terminals on a work order basis throughout District 1.
|
008-62U04
|
Deleted
|
10/12/2022
|
|
|
1
|
1
|
Cook
|
|
(2100-Ft) SMART overlay project on IL Route 43 from Sanitary and Ship Canal to Hanover Street, located in Village of Summit, Village of Forest View, and City of Chicago in Cook County.
|
009-64G66
|
Executed
|
12/20/2022
|
1 / 1 |
|
2
|
2
|
Whiteside
|
|
7.5 MI CIP RS and Culvert Replacement, Culvert Extension from the Carroll County Line to US 30.
|
010-64H57
|
Executed
|
12/20/2022
|
2 / 2 |
1 |
2
|
2
|
Ogle
|
|
Remove and replace (SN 071-0070) over Elkhorn Creek 0.5 m (s) of IL 64 near Brookville.
|
011-64R12
|
Executed
|
12/20/2022
|
1 / 1 |
1 |
2
|
2
|
Ogle
|
|
Bridge deck overlay, expansion joint replacement and miscellaneous repairs on SN 071-0072 carrying IL 2 over drainage ditch 2 miles North of Grand Detour at the Whiteside County Line.
|
012-64R51
|
Executed
|
12/20/2022
|
|
|
2
|
2
|
Carroll
|
|
Beam end repairs, expansion joint replacement and installation of concrete wearing surface on SN 008-0015 carrying IL 84 over Rush Creek, 3.1 miles South of JoDaviess County line.
|
013-64R73
|
Executed
|
12/20/2022
|
|
1 |
2
|
2
|
Winnebago
|
|
Washing the 2 bridges (SN 101-0133 and 101-0134) carrying I-39 over the Kishwaukee River.
|
014-64R74
|
Executed
|
12/27/2022
|
|
1 |
2
|
2
|
Boone, Winnebago
|
|
Washing nine bridges at various locations in Boone and Winnebago Counties.
|
015-64R75
|
Executed
|
12/27/2022
|
|
1 |
2
|
2
|
Various
|
|
Washing seventeen bridges at various locations in Carroll, Ogle, Stephenson, and Whiteside Counties.
|
016-64R76
|
Executed
|
01/03/2023
|
|
1 |
2
|
2
|
Various
|
|
Washing twelve bridges at various locations in Henry, Lee, Rock Island and Whiteside Counties.
|
017-64R80
|
Executed
|
01/03/2023
|
|
1 |
2
|
2
|
Rock Island
|
|
Washing the bridge (SN 081-0011) carrying I-80 over the Mississippi River.
|
018-64R81
|
Executed
|
01/03/2023
|
|
1 |
2
|
2
|
Various
|
|
Washing three bridges over the Mississippi River, Carroll County (SN 008-0052) carrying US 52/IL 64, Rock Island County (SN 081-9905) carrying US 67 and Whiteside County (SN 098-6003) carrying US 30.
|
019-64R82
|
Executed
|
01/03/2023
|
|
1 |
2
|
2
|
Various
|
|
Washing six bridges over the Rock River in Henry, Rock Island, and Whiteside Counties.
|
020-64R83
|
Executed
|
01/03/2023
|
|
1 |
2
|
2
|
Henry, Rock Island
|
|
Washing five bridges over the Rock River in Henry and Rock Island Counties.
|
021-64R84
|
Executed
|
01/03/2023
|
|
1 |
2
|
2
|
Various
|
|
Washing eight bridges at various locations in Henry, Lee, Ogle, Stephenson, and Whiteside Counties.
|
022-66E96
|
Executed
|
01/03/2023
|
1 / 1 |
|
2
|
3
|
Kendall
|
|
.01 mi culvert replacement SN 047-2517 Stream 0.4 mi N of Chicago Rd.
|
023-66F20
|
Executed
|
12/20/2022
|
1 / 1 |
1 |
2
|
3
|
Kankakee
|
|
Work begins on IL 115 1/3 miles north of Gar Creek in southwest Kankakee and ends at the intersection of S Washington Avenue and W Jeffery Street in Kankakee. The project is a milling and resurfacing with a designed overlay of IL 115 including drainage and ADA improvements.
|
024-66M31
|
Executed
|
12/20/2022
|
|
1 |
2
|
3
|
Bureau
|
|
This project is located on FAP 587 (US 34) beginning N. of LaMoille and ending at the LaSalle County line,_for a total of 5.85 miles. Work consists of milling and resurfacing 1 1/2" (SMART), aggregate shoulders, guardrail work, pavement marking, and raised reflectors.
|
025-66M38
|
Executed
|
01/06/2023
|
|
1 |
2
|
3
|
Iroquois
|
|
This project consists of 5.3 miles of shoulder widening and rumble strip installation on IL 1 from 0.02 mi South of E 2500N Rd to 0.22 mi North of E 1950N Rd in Iroquois County.
|
026-68E43
|
Executed
|
12/27/2022
|
4 / 4 |
1 |
3
|
4
|
Warren
|
|
This project is located just west of Galesburg and consists of replacing a double steel plate arch culvert with a double 12'x12' precast concrete box culvert carrying US 34 over the South branch of Cedar Creek.
|
027-68F08
|
Executed
|
12/27/2022
|
3 / 3 |
1 |
3
|
4
|
Marshall
|
|
Bridge painting and rehabilitation to S.N. 062-0003 carrying IL 17 over the Illinois River in Lacon.
|
028-68F38
|
Executed
|
12/27/2022
|
6 / 6 |
1 |
3
|
4
|
Peoria, Tazewell
|
|
Bridge Rehabilitation with bridge deck overlay, beam repairs, beam additions, navigation and roadway lighting, traffic signal improvements, drainage improvements, full depth pavement removal and replacement, sidewalk removals, multi-use path construction and related collateral work. Bob Michel Bridge (SN 090-0122) in Peoria and Tazewell Counties on IL 40 (William Kumpf Blvd.) over the Illinois River and Washington Street.
|
029-70604
|
Executed
|
12/27/2022
|
|
1 |
3
|
5
|
Champaign
|
|
50.5 FT=0.010 Ml, BRIDGE SUPERSTRUCTURE REPLACEMENT, LOCATED AT LONG POINT SLOUGH 0.1 Ml N OF LONGVIEW NCL.
|
030-70F43
|
Executed
|
12/27/2022
|
|
1 |
3
|
5
|
Various
|
|
Bridge Painting at 11 Structure Locations on Various Routes in Champaign, Mclean, and Piatt Counties.
|
031-72022
|
Executed
|
12/27/2022
|
|
|
4
|
6
|
Various
|
|
Lot improvements at the Barry, Divernon, Havana, Mason City and Taylorville Maintenance Yards.
|
032-72033
|
Executed
|
12/20/2022
|
|
|
4
|
6
|
Sangamon
|
|
This work shall consist of painting SN 084-0152 and 0153, carrying I-72 over the Sangamon River, East of Springfield in Sangamon County.
|
033-72119
|
Executed
|
01/20/2023
|
3 / 3 |
|
4
|
6
|
Morgan
|
|
Tree removal on IL 104 from 0.1 miles northwest of Waverly Lake Road / Gordon Hill Road to 0.2 miles east of Woods Creek.
|
034-72595
|
Executed
|
01/03/2023
|
|
|
4
|
6
|
Macoupin
|
|
This work shall consist of painting four bridges carrying various routes over I-55 in southern Macoupin County.
|
035-72C24
|
Executed
|
01/03/2023
|
4 / 4 |
1 |
4
|
6
|
Brown
|
|
9.83 Mile Cape Seal and Grinding of IL 107 from Mt. Sterling to Pike County Line.
|
036-72D32
|
Executed
|
12/27/2022
|
|
|
4
|
6
|
Montgomery
|
|
5 miles of milling, patching and resurfacing on I-55 from 1.3 miles south of Waggoner to 0.6 miles north of IL 108.
|
037-72F26
|
Withdrawn
|
10/21/2022
|
|
|
4
|
6
|
Adams
|
|
Culvert Replacement, Ditch 1 Mile North of Kochs Lane North of Quincy IL.
|
038-72M49
|
Withdrawn
|
11/16/2022
|
|
1 |
4
|
6
|
Cass
|
|
Concrete microsilica overlay, bridge joint replacement and bridge repair on IL 125 over the BNSF Railroad in Beardstown.
|
039-72N46
|
Executed
|
12/27/2022
|
|
|
4
|
6
|
Sangamon
|
|
Hydroscarification with Microsilica Overlay on bridge deck and approaches on structure SN 084-0508 along IL-4 over Sugar Creek in Sangamon County, and guardrail replacement.
|
040-72N47
|
Executed
|
12/20/2022
|
|
|
4
|
6
|
Hancock
|
|
(0.00) Bridge Deck Overlay, Rocky Run Creek 4.7 Mile North of Adams Co line.
|
041-72N48
|
Executed
|
12/27/2022
|
|
|
4
|
6
|
Pike
|
|
0.08 miles, Concrete microsilica overlay of bridge deck and approach pavements, Kiser Creek 4.5 miles East of CH 4 in Barry.
|
042-72N49
|
Executed
|
12/27/2022
|
1 / 1 |
|
4
|
6
|
Pike
|
|
0.47 miles, Concrete microsilica overlay of bridge decks and HMA overlay of approach pavements, Walnut Creek Ditch and Pigeon Creek 2.2 and 2.5 miles West of IL 96.
|
043-74352
|
Executed
|
01/03/2023
|
1 / 1 |
|
4
|
7
|
Effingham
|
|
Project length is 0.17 miles. Removal and replacement of SN 025-0065 with HMA resurfacing, earthwork, riprap, guardrail, pavement marking, etc. SN 025-0065 is located on IL 128 over Big Moccasin Creek, 4.3 miles south of IL 33.
|
044-74362
|
Executed
|
01/10/2023
|
|
|
4
|
7
|
Coles
|
|
Bridge replacement for SN 015-0022 carrying US 45 over Flat Branch, 0.1 miles south of South-Side Drive in Humboldt.
|
045-74574
|
Withdrawn
|
10/14/2022
|
|
|
4
|
7
|
Wayne
|
|
Patching, milling, resurfacing, designed overlay, ADA improvements and traffic signals on US 45 / IL 15 in Fairfield, eastbound from SW 7th to SE 9th and westbound from SE 9th to 0.1 miles west of Market Street.
|
046-74755
|
Executed
|
01/06/2023
|
|
|
4
|
7
|
Crawford
|
|
Replacement of SN 017-0022 carrying IL 1 over an unnamed creek, 1.8 miles South of IL 33.
|
047-74983
|
Executed
|
01/03/2023
|
3 / 3 |
1 |
4
|
7
|
Fayette
|
|
New bridge deck, bridge approach slab replacement, bridge joint repair and replacement, and crash wall repairs on SN 026-0032 carrying US 51 over I-70 in Vandalia.
|
048-74A70
|
Executed
|
01/03/2023
|
1 / 1 |
1 |
4
|
7
|
Coles
|
|
This project is located on 1-57 over S Fork Branch 0.5 miles S of Humboldt. The work consists of replacing the approach slabs, bridge wearing surfaces, and joints on SN 015-0009 and 015-0010.
|
049-74A71
|
Executed
|
01/10/2023
|
|
|
4
|
7
|
Cumberland
|
|
Bridge Deck Overlay, Deck Repairs, Joint Replacement and Repair on FAI Route 70 over Range Creek.
|
050-74A90
|
Executed
|
01/03/2023
|
|
|
4
|
7
|
Effingham
|
|
Bridge deck overlay, bridge joint repair and replacement and bridge deck patching on SN 025-0079 carrying US 40 over the Little Wabash River, 2 miles west of Effingham.
|
051-74A92
|
Executed
|
01/03/2023
|
|
1 |
4
|
7
|
Fayette
|
|
Bridge joint replacement, deck repair and overlay on 4 bridges on US 40 on the west side of Fayette County. (SN 026-0042, 026-0044, 026-0045 and 026-0046)
|
052-76K25
|
Executed
|
01/03/2023
|
|
|
5
|
8
|
Randolph
|
|
Replacing SN 079-0005 carrying IL 3 over Nine Mile Creek, 4 miles south of Evansville.
|
053-76M43
|
Withdrawn
|
11/16/2022
|
|
|
5
|
8
|
Jersey
|
|
Culvert repairs on SN042-2417 carrying Old US 67 over a Tributary to Piasa Creek, 0.1 miles north of New Delhi Road.
|
054-76M79
|
Executed
|
01/03/2023
|
3 / 3 |
1 |
5
|
8
|
Madison
|
|
6.87 miles of standard overlay resurfacing, ADA improvements, patching, guardrail improvements and detector loop replacement on US 40 / IL 143 in Highland.
|
055-76R44
|
Executed
|
01/03/2023
|
|
1 |
5
|
8
|
Various
|
|
Broadlead weed spraying on various interstates in various counties of District.
|
056-78719
|
Executed
|
01/13/2023
|
2 / 2 |
|
5
|
9
|
Pope
|
|
Bridge replacement project on IL 145, approximately 2.3 miles south of the IL 145 / IL 146 intersection. (SN 076-0024)
|
057-78893
|
Executed
|
01/10/2023
|
1 / 1 |
|
5
|
9
|
Franklin
|
|
Replacement of 5 box culverts on IL 34 between Benton and Thompsonville.
|
058-78930
|
Executed
|
01/13/2023
|
1 / 1 |
1 |
5
|
9
|
Franklin
|
|
Proposed improvements consist of joint reconstruction, hydro-scarification with microsilica concrete overlay, bearing replacement and approach slab repair on SN 028-0063, W. Webster St. over 1-57 in Franklin County.
|
059-78957
|
Executed
|
01/03/2023
|
2 / 2 |
1 |
5
|
9
|
Williamson
|
|
This project involves the construction of a mid-block crosswalk with ADA ramps, median refuge island, rectangular rapid flashing beacons, highway lighting and appropriate pavement markings on IL 13 at Ray Fosse Park in Marion IL.
|
060-46610
|
Executed
|
01/10/2023
|
|
|
3
|
5
|
Various
|
|
Removing reflectors, placing new reflectors, removing damaged RRPM castings, and placing new RRPM castings.
|
061-46934
|
Executed
|
02/10/2023
|
7 / 7 |
|
2
|
2
|
Winnebago
|
|
The proposed improvements consist of road reconstruction, culvert replacement, ADA and parking improvements, and all other work to complete the improvement at INDR's Rock Cut State Park located in Winnebago County.
|
062-46935
|
Executed
|
01/03/2023
|
|
|
5
|
8
|
Washington
|
|
Construction of a new entrance road on new alignment at the Washington County State Recreation Area.
|
063-62N41
|
Executed
|
01/03/2023
|
2 / 2 |
1 |
1
|
1
|
Will
|
|
(1,195-Ff) Removal of existing 4-span bridge along Shepley Road over I-80 in Will County, IL and replacement with a 2-span 264'-00" long, 36'-10" out to out wide bridge. Bridge approach roadway improvements include pavement reconstruction, shoulder construction, guardrail replacement, and maintenance of traffic control.
|
064-62R67
|
Executed
|
12/27/2022
|
|
|
1
|
1
|
Cook
|
|
(300-Ft) The improvement consists of substructure and joint repairs of structure carrying 87th Street (SN 016-1142) over the 1-94 (Dan Ryan Expressway ) in the City of Chicago, Cook County.
|
065-62U33
|
Active
|
09/28/2022
|
|
|
1
|
1
|
Various
|
|
The work to be completed under this contract consists of expressway daytime sweeping throughout the northern half of District 1.
|
066-62U34
|
Executed
|
12/20/2022
|
|
1 |
1
|
1
|
Various
|
|
The improvement consists of tree removal in various counties in District 1.
|
067-64G68
|
Executed
|
01/03/2023
|
8 / 8 |
1 |
2
|
2
|
Winnebago
|
|
Replace the four-span bridge (SN 101-0098) carrying Perryville Road over I-39 with a two-span continuous, steel plate girder bridge.
|
068-64R98
|
Executed
|
01/13/2023
|
|
|
2
|
2
|
Stephenson
|
|
0.8 mile Class B patching from North of Fairgrounds Road to South Street in Freeport.
|
069-64S06
|
Executed
|
12/20/2022
|
|
|
2
|
2
|
Whiteside
|
|
Pavement patching from Rock lsland/Whiteside County line to 3.10 mile North East.
|
070-66M51
|
Executed
|
12/27/2022
|
1 / 1 |
|
2
|
3
|
LaSalle
|
|
Structure No. 050-2574, Box Culvert Rehabilitation, 2.47 miles north of US Route 52.
|
071-66M74
|
Executed
|
12/20/2022
|
|
|
2
|
3
|
Bureau
|
|
Structure No. 006-0153, Bridge Rehabilitation, 3.3 mi. west of US 34 (Lamoille).
|
072-68E32
|
Executed
|
01/03/2023
|
|
|
3
|
4
|
Peoria
|
|
Project consists of the culvert rehabilitation of SN 072-2008, a double 10' x 10' box culvert, at Big Hollow Creek on US 150 (War Memorial) in Peoria.
|
073-68F51
|
Executed
|
01/03/2023
|
|
|
3
|
4
|
Marshall
|
|
Shoulder, foreslope repair, replace guardrail and culvert extensions on IL 17, 1.5 mi. W. Sparland, Sta. 463+00.
|
074-72027
|
Executed
|
12/20/2022
|
|
|
4
|
6
|
Morgan
|
|
Bridge bearing replacement on four I-72 structures near Jacksonville. (SN069-0042, 069-0043, 069-0047, 069-0050)
|
075-72099
|
Executed
|
01/27/2023
|
1 / 1 |
|
4
|
6
|
Sangamon
|
|
Tree removal and fencing at the northbound and southbound I-55 Railsplitter Rest Areas.
|
076-72246
|
Executed
|
01/10/2023
|
|
1 |
4
|
6
|
Sangamon
|
|
Installation of CCTV cameras, conduit, handholes and fiber optic cable at various locations in Springfield and Chatham.
|
077-72H71
|
Executed
|
01/27/2023
|
1 / 1 |
|
4
|
6
|
Sangamon
|
|
2.3 miles of sidewalk, ADA ramps and roadway lighting improvements on Business 55, IL 29 / Peoria Road from Sangamon Avenue to Ardmore Avenue in Springfield.
|
078-78372
|
Executed
|
01/13/2023
|
|
1 |
5
|
9
|
Jackson, Williamson
|
|
Intersection improvements, pavement widening, HMA resurfacing and a multi-use path on IL 13 from the Williamson County line to east of Spillway Road.
|
079-78909
|
Deleted
|
10/13/2022
|
|
|
5
|
9
|
Saline
|
|
Signal modifications and ADA improvements at the intersection of Old IL 13 and Main Street in Harrisburg.
|
080-78962
|
Active
|
09/28/2022
|
1 / 1 |
|
5
|
9
|
Franklin
|
|
Replacement of the sanitary sewer lift station and grinder, electrical service, alarm system, driveway pavement and water service at northbound I-57 Rend Lake Rest Area, 2.4 miles north of the IL 14 / Benton interchange.
|
081-61G82
|
Executed
|
12/20/2022
|
13 / 13 |
3 |
1
|
1
|
DuPage
|
|
Removal of existing structure and construciton of two span post-tensioned cast-in-place concrete superstructure bridge on cast-in-place concrete substructure, with HMA removal and replacement, PCC sidewalk with ADA improvements, class D patching, curb and gutter, storm sewer, street scaping, and traffic signals on Washington Street over west branch of DuPage River in Naperville.
|
082-61H12
|
Executed
|
01/17/2023
|
1 / 1 |
|
1
|
1
|
Cook
|
|
Sidewalk construction, segmental concrete block wall and pedestrian signal improvements on Midlothian Turnpike from Central Avenue to Pulaski Road in Crestwood.
|
083-61H33
|
Executed
|
01/03/2023
|
2 / 2 |
2 |
1
|
1
|
Lake
|
|
Replace the bridge carrying Park Avenue West over a Ditch of the Skokie River in Highland Park.
|
084-61H52
|
Executed
|
01/10/2023
|
|
|
1
|
1
|
DuPage
|
|
Construction of HMA bike path, grading, and seeding along Lies Road from Gary Avenue to Schmale Road in Carol Stream.
|
085-61H56
|
Executed
|
01/10/2023
|
|
|
1
|
1
|
Cook
|
|
HMA bike path along the east parkway of Quentin Road from Euclid Avenue to Hartung Road, and along the north parkway of Hartun Road from Quentin Road to Old Plum Grove Road in Rolling Meadows.
|
086-61H89
|
Executed
|
01/06/2023
|
|
|
1
|
1
|
Cook
|
|
Resurface 144th Street from Indiana Avenue to Chicago Road in the Village of Dolton.
|
087-61J00
|
Executed
|
12/20/2022
|
1 / 1 |
1 |
1
|
1
|
Cook
|
|
.99 miles of HMA surface removal and resurfacing with Class D Patches, concrete curb and ugtter removal and replacement, and pavement marking on 94th Avenue from 159th Street to 151 Street in Orland Park.
|
088-61J02
|
Executed
|
01/03/2023
|
2 / 2 |
2 |
1
|
1
|
Cook
|
|
Pavement reconstruction, traffic signal modernization, and lighting improvement on Washington Boulevard from 21st Avenue to 9th Avenue in Maywood.
|
089-61J03
|
Executed
|
12/20/2022
|
1 / 1 |
|
1
|
1
|
McHenry
|
|
Resurfacing and sidewalk construction on Green Street from IL 120 to Municipal Drive in McHenry
|
090-61J05
|
Rejected
|
01/17/2023
|
1 / 1 |
|
1
|
1
|
Lake
|
|
Resurfacing Telegraph Road from the north village limits to North Avenue, and placement of a bike path/sidewalk south of IL 22 in Bannockburn.
|
091-62R49
|
Active
|
09/29/2022
|
|
|
1
|
1
|
Various
|
|
The work to be completed under this contract consists expressway daytime sweeping throughout the southern half of District 1.
|
092-85728
|
Executed
|
01/03/2023
|
|
|
2
|
2
|
Rock Island
|
|
Removal of existing steel pile retaining walk and construction of a 330' drilled shaft foundation retaining wall supporting concrete columns and web walls with HMA pavement removal and replacement, aggregate shoulders, reshaping of ditches, and grading along county highway 11 in Rock Island County .
|
093-87768
|
Executed
|
01/03/2023
|
|
|
2
|
3
|
Grundy
|
|
Replace superstructure carrying Brisbin Road over Collins Run Creek, 1.4 miles south of Minooka.
|
094-87769
|
Rejected
|
12/05/2022
|
|
|
2
|
3
|
Iroquois
|
|
Replace the bridge carrying 1000 East Road over a tributary to Little Mud Creek 3 miles northwest of Cissna Park
|
095-89796
|
Executed
|
12/27/2022
|
6 / 5 |
|
3
|
4
|
Fulton
|
|
Replace the bridge carrying CH 2 over Otter Creek, 4 miles north of Astoria.
|
096-93796
|
Executed
|
12/20/2022
|
|
|
4
|
6
|
Scott
|
|
Replace the bridge carrying CH 12 over Mauvaise Terre Creek, 1.5 miles east of Exeter.
|
097-97781
|
Executed
|
01/03/2023
|
1 / 1 |
|
5
|
8
|
Marion
|
|
HMA surface course and bind course on a processed modified soil cement base, also culvert and storm replacement on Heinzmann Road from IL 161 extension to Kell Road.
|
098-97792
|
Executed
|
01/06/2023
|
|
|
5
|
8
|
Madison
|
|
.52 miles of pavement patching, HMA removal and resurfacing, drainage repairs, and ADA curb ramps on State Street from Rozier Street to Logan Street in Alton.
|
099-99671
|
Executed
|
01/03/2023
|
3 / 2 |
1 |
5
|
9
|
Franklin
|
|
.55 miles of PCC and HMA pavement road reconstruction, concrete curb and gutter, and storm sewer construction on Wastena Street from IL 37 to South McLeansboro Street in Benton.
|
100-99696
|
Executed
|
01/10/2023
|
|
|
5
|
9
|
Massac
|
|
Resurfacing CH 5 from CH 4 to the east city limits of Joppa.
|
101-61H20
|
Executed
|
01/10/2023
|
2 / 2 |
|
1
|
1
|
Will
|
|
Reconstruction and widening of Laraway Road between Jackson Branch Creek and Cedar Road.
|
102-64M81
|
Executed
|
01/13/2023
|
|
|
2
|
2
|
Rock Island
|
|
4.28 miles, cold milling, pavement patching and Hot-Mix Asphalt resurfacing on I-280 from East of the IL 92_interchange to 0.1 miles East of Milan Beltway.
|
103-68698
|
Withdrawn
|
11/15/2022
|
2 / 2 |
1 |
3
|
4
|
Stark
|
|
Replacement of the structure carrying IL 17/ IL 91 over the Spoon River SN 088-0002 (existing; SN 088-0030 (proposed)Ù, 0.6 miles West of Wyoming in Stark County. The project is 2887 feet (0.55 mile) in length. The project also includes roadway profile adjustments, regrading of sideslopes, and construction of the stream barbs.
|
104-74A69
|
Executed
|
01/10/2023
|
4 / 4 |
2 |
4
|
7
|
Effingham
|
|
Bridge joint repairs, bridge deck patching, slope wall replacement and bridge deck scarification and overlay at the I-57 / I-70 tri-level southwest of Effingham.
|
105-78958
|
Active
|
10/04/2022
|
|
|
5
|
9
|
Franklin
|
|
Replacement of the pumps, piping, back-up and electrical controls of the pump station along I-57 at the West Frankfort interchange.
|
106-87810
|
Executed
|
12/20/2022
|
|
|
2
|
3
|
LaSalle
|
|
Construction of a soldier pile wall and slope stabilization along North 2550th Road from North 2551st Road to a point approximently 0.25 mile east along 2550th Road in the Peru Road District.
|
107-93691
|
Executed
|
01/06/2023
|
5 / 5 |
|
4
|
6
|
Sangamon
|
|
Reconstruction of Stanford Avenue from 11th Street to Fox Bridge Road including the construction of a pedestrian path, in Springfield.
|
108-97790
|
Withdrawn
|
10/27/2022
|
|
|
5
|
8
|
Madison
|
|
Reconstruction of Lebanon Road on new alignment to facilitate closure of two underpass structures. Work includes structure removal, construction of a 6-span steel plate girder bridge, construction of a 1-span PC slab bridge, box culverts, pavment removal, building removal, processing lime modified soil, PPC pavement, HMA pavement, HMA shoulders, combination curb and gutter, storm sewer, and other necessary work.
|
109-99692
|
Executed
|
01/03/2023
|
3 / 2 |
1 |
5
|
9
|
Jefferson
|
|
Resurfacing, HMA shoulders and rumble strips on Dix Irvington Road from east of US 51 to Boyd Road.
|
110-72B64
|
Executed
|
01/13/2023
|
2 / 2 |
1 |
4
|
6
|
Macoupin
|
|
3 bridge replacements on IL 16: 1. Over Piasa Creek, 0.2 miles west of Piasa; 2. Over Piasa Creek Tributary, 3.2 miles west of Shipman; 3. Over Piasa Creek, 3.1 miles west of Shipman. (SN 059-0001, 059-0002, 059-7039)
|
01A-FR046
|
Executed
|
05/19/2023
|
|
|
2
|
2
|
Stephenson
|
|
Rehabilitate Taxiway A Pavement, East of Taxiway G and West of Taxiway C, and Rehabilitate Taxiway D and Taxiway G
|
02A-FA008
|
Withdrawn
|
10/20/2022
|
|
|
4
|
7
|
Wayne
|
|
Ramp Expansion and Airfield Drainage Improvements
|
03A-AU071
|
Executed
|
10/24/2023
|
|
|
1
|
1
|
Kane
|
|
Airfield Pavement Rehabilitation - Phase 4
|
04A-WA078
|
Executed
|
08/16/2023
|
|
|
1
|
1
|
Lake
|
|
Rehabilitate Hangar Pavements in South Hangar Area - Phase 1
|