Construction of a multi-use trail with trail head parking area between Irwin Bridge Road an Ethell Road. Work includes aggregate base course, shoulders, HMA surface course, pipe culverts, pavment markings, signage, erosion control, bicycle railing and so much more.
Region District DBE % VBP % Federal Project #
4 6 6.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Menard
  • SANGAMON
  • VALLEY
  • TRAIL
  • 18-00068-00-BT
  • C-96-036-25
  • 0-02272-6002
Contract Specifics
85 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 2 Answered ) Questions not accepted as of January 07, 2025 04:30 PM.

  • According to the special provisions, under the Traffic Control Plan, it states the multi-use trail shall be closed to all traffic, bicycles, and pedestrians for the duration of the contract. It states this work shall be included in the contract unit bid price per cubic yard for Earth Excavation. Should this be priced under the BLR-21 pay item? Please clearify.
    • Placing and maintaining Type III Barricades with Road Closed signs on the existing and proposed trail alignment at both sides of the township road intersections, as applicable, during construction shall be part of the Earth Excavation bid item. These shall be in place for the full duration of the construction and then removed and remain the property of the Contractor when the trail is open and after permanent bollards are in place to block traffic from using the trail. • Placing, maintaining, and removing TC&P per Standard BLR-21 for short durations only as necessary on the actual township roads (when concrete, aggregate, and HMA material are placed for the trail up to the edges of the existing township roads) during the actual construction of the intersections shall be part of the BLR-21 pay item. (12/16/2024)

  • The bollards call for sheeting to be around them. How tall is this sheeting supposed to be? Typically it has been 24" tall chevron sheeting applied to the circumference. Will this be acceptable or will the sheeting need to be applied 2 the whole visible section of the bollards?
    The covering is to be applied to the entire bollard. (12/11/2024)

Authorized Bidders

  • 2825 Illinois Valley Paving, a div of UCM, Inc.
    3151 Robbins Road
    Springfield, IL 62704
    P.O. Box 13420
    Springfield, IL 62791
    Phone: (217) 546-6192 Fax: (217) 546-1904 Email: IVP@ucm.biz

  • 3163 Kinney Contractors, Inc.
    19342 E. Frontage Rd.
    Raymond, IL 62560
    Phone: (217) 229-3322 Fax: (217) 229-3609 Email: kinney@roadbuilder.net

  • 0335 Otto Baum Company, Inc.
    866 N. Main Street
    Morton, IL 61550
    Phone: (309) 266-7114 Fax: (309) 263-1050 Email: timgillette@ottobaum.com

  • 5310 Sangamo Construction Company
    2100 East Moffat St
    Springfield, IL 62702
    Phone: (217) 544-9871 Fax: (217) 544-9873 Email: office@sangamo.net

  • 0958 William Charles Construction Company, LLC
    833 Featherstone Road
    Rockford, IL 61107
    P.O. Box 2071
    Loves Park, IL 61130
    Phone: (815) 654-4700 Fax: (815) 654-4736 Email: bids@williamcharles.com

Non Bidders

  • 3391 Laverdiere Construction, Inc.
    (Pending Authorization)
    4055 W Jackson St
    Macomb, IL 61455
    Phone: (309) 837-1258 Fax: (309) 833-4993 Email: mlynn@lavconinc.com

  • 4991 Rees Construction Company of Quincy
    (Pending Authorization)
    517 Kentucky
    Quincy, IL 62301
    P.O. Box 646
    Quincy, IL 62306
    Phone: (217) 222-0748 Fax: (217) 222-2613 Email: info@reesconstructionco.com

Pay Item # UOM Description Type Quantity Unit Price
20200100 CU YD EARTH EXCAVATION Base items 8,934.000
20800150 CU YD TRENCH BACKFILL Base items 21.000
28000250 POUND TEMPORARY EROSION CONTROL SEEDING Base items 514.000
28000305 FOOT TEMPORARY DITCH CHECKS Base items 100.000
28000400 FOOT PERIMETER EROSION BARRIER Base items 500.000
28000500 EACH INLET AND PIPE PROTECTION Base items 6.000
35101800 SQ YD AGGREGATE BASE COURSE, TYPE B 6" Base items 16,848.000
35102000 SQ YD AGGREGATE BASE COURSE, TYPE B 8" Base items 920.000
40600290 POUND BITUMINOUS MATERIALS (TACK COAT) Base items 189.000
40603080 TON HOT-MIX ASPHALT BINDER COURSE, IL-19.0, N50 Base items 124.000
40604050 TON HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "C", N50 Base items 2,109.000
42000060 SQ YD WELDED WIRE REINFORCEMENT Base items 210.000
42400410 SQ FT PORTLAND CEMENT CONCRETE SIDEWALK 8 INCH Base items 1,886.000
42400800 SQ FT DETECTABLE WARNINGS Base items 248.000
48101498 SQ YD AGGREGATE SHOULDERS, TYPE B 4" Base items 82.000
50102400 CU YD CONCRETE REMOVAL Base items 2.000
50105220 FOOT PIPE CULVERT REMOVAL Base items 62.000
54213663 EACH PRECAST REINFORCED CONCRETE FLARED END SECTIONS 18" Base items 12.000
542A0223 FOOT PIPE CULVERTS, CLASS A, TYPE 1 18" Base items 168.000
67100100 L SUM MOBILIZATION Base items 1.000
72000100 SQ FT SIGN PANEL - TYPE 1 Base items 108.000
72000200 SQ FT SIGN PANEL - TYPE 2 Base items 38.000
72500400 EACH OBJECT MARKER - TYPE 4 Base items 2.000
72800100 FOOT TELESCOPING STEEL SIGN SUPPORT Base items 422.000
78001100 SQ FT PAINT PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 66.000
78001110 FOOT PAINT PAVEMENT MARKING - LINE 4" Base items 1,038.000
78001180 FOOT PAINT PAVEMENT MARKING - LINE 24" Base items 42.000
X0321158 EACH PARK BENCHES Base items 1.000
X0322135 EACH BOLLARDS, QUICK RELEASE Base items 7.000
X0323378 EACH CONCRETE PARKING BLOCKS Base items 18.000
X2010510 L SUM CLEARING AND GRUBBING Base items 1.000
X2501000 ACRE SEEDING, CLASS 2 (SPECIAL) Base items 5.200
X4811800 SQ YD AGGREGATE SHOULDERS (SPECIAL) Base items 4,865.000
X5091725 FOOT BICYCLE RAILING (SPECIAL) Base items 800.000
X7011800 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD BLR 21 Base items 1.000
Z0003855 EACH BICYCLE RACKS Base items 1.000
Z0004002 EACH BOLLARDS Base items 18.000
Z0013798 L SUM CONSTRUCTION LAYOUT Base items 1.000
No More Pay Items