Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 6 | 6.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
85 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 8,934.000 | |||
20800150 | CU YD | TRENCH BACKFILL | Base items | 21.000 | |||
28000250 | POUND | TEMPORARY EROSION CONTROL SEEDING | Base items | 514.000 | |||
28000305 | FOOT | TEMPORARY DITCH CHECKS | Base items | 100.000 | |||
28000400 | FOOT | PERIMETER EROSION BARRIER | Base items | 500.000 | |||
28000500 | EACH | INLET AND PIPE PROTECTION | Base items | 6.000 | |||
35101800 | SQ YD | AGGREGATE BASE COURSE, TYPE B 6" | Base items | 16,848.000 | |||
35102000 | SQ YD | AGGREGATE BASE COURSE, TYPE B 8" | Base items | 920.000 | |||
40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 189.000 | |||
40603080 | TON | HOT-MIX ASPHALT BINDER COURSE, IL-19.0, N50 | Base items | 124.000 | |||
40604050 | TON | HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "C", N50 | Base items | 2,109.000 | |||
42000060 | SQ YD | WELDED WIRE REINFORCEMENT | Base items | 210.000 | |||
42400410 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 8 INCH | Base items | 1,886.000 | |||
42400800 | SQ FT | DETECTABLE WARNINGS | Base items | 248.000 | |||
48101498 | SQ YD | AGGREGATE SHOULDERS, TYPE B 4" | Base items | 82.000 | |||
50102400 | CU YD | CONCRETE REMOVAL | Base items | 2.000 | |||
50105220 | FOOT | PIPE CULVERT REMOVAL | Base items | 62.000 | |||
54213663 | EACH | PRECAST REINFORCED CONCRETE FLARED END SECTIONS 18" | Base items | 12.000 | |||
542A0223 | FOOT | PIPE CULVERTS, CLASS A, TYPE 1 18" | Base items | 168.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
72000100 | SQ FT | SIGN PANEL - TYPE 1 | Base items | 108.000 | |||
72000200 | SQ FT | SIGN PANEL - TYPE 2 | Base items | 38.000 | |||
72500400 | EACH | OBJECT MARKER - TYPE 4 | Base items | 2.000 | |||
72800100 | FOOT | TELESCOPING STEEL SIGN SUPPORT | Base items | 422.000 | |||
78001100 | SQ FT | PAINT PAVEMENT MARKING - LETTERS AND SYMBOLS | Base items | 66.000 | |||
78001110 | FOOT | PAINT PAVEMENT MARKING - LINE 4" | Base items | 1,038.000 | |||
78001180 | FOOT | PAINT PAVEMENT MARKING - LINE 24" | Base items | 42.000 | |||
X0321158 | EACH | PARK BENCHES | Base items | 1.000 | |||
X0322135 | EACH | BOLLARDS, QUICK RELEASE | Base items | 7.000 | |||
X0323378 | EACH | CONCRETE PARKING BLOCKS | Base items | 18.000 | |||
X2010510 | L SUM | CLEARING AND GRUBBING | Base items | 1.000 | |||
X2501000 | ACRE | SEEDING, CLASS 2 (SPECIAL) | Base items | 5.200 | |||
X4811800 | SQ YD | AGGREGATE SHOULDERS (SPECIAL) | Base items | 4,865.000 | |||
X5091725 | FOOT | BICYCLE RAILING (SPECIAL) | Base items | 800.000 | |||
X7011800 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD BLR 21 | Base items | 1.000 | |||
Z0003855 | EACH | BICYCLE RACKS | Base items | 1.000 | |||
Z0004002 | EACH | BOLLARDS | Base items | 18.000 | |||
Z0013798 | L SUM | CONSTRUCTION LAYOUT | Base items | 1.000 | |||
No More Pay Items |