| Region | District | DBE % | VBP % | Federal Project # | 
|---|---|---|---|---|
| 4 | 6 | 0.00 | 0.00 | 
| County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) | 
|---|---|---|---|---|---|
| 
 | 
 | 
 | 
 | 
 | 
 | 
| Contract Specifics | 
|---|
| 15 Working Days | 
| No More Contract Specifics | 
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| 28100209 | TON | STONE RIPRAP, CLASS A5 | Base items | 600.000 | |||
| 28100807 | TON | STONE DUMPED RIPRAP, CLASS A4 | Base items | 100.000 | |||
| 28200200 | SQ YD | FILTER FABRIC | Base items | 422.000 | |||
| 67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| 70100800 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701401 | Base items | 1.000 | |||
| 70107025 | CAL DA | CHANGEABLE MESSAGE SIGN | Base items | 7.000 | |||
| No More Pay Items | |||||||