Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
2 | 3 | 0.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
20 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 23.000 | |||
21001000 | SQ YD | GEOTECHNICAL FABRIC FOR GROUND STABILIZATION | Base items | 75.000 | |||
35102000 | SQ YD | AGGREGATE BASE COURSE, TYPE B 8" | Base items | 75.000 | |||
35800200 | TON | AGGREGATE BASE REPAIR | Base items | 75.000 | |||
40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 156.000 | |||
40600906 | TON | POLYMERIZED HOT-MIX ASPHALT BINDER COURSE (HAND METHOD), N70 | Base items | 10.000 | |||
40600990 | SQ YD | TEMPORARY RAMP | Base items | 290.000 | |||
40603235 | TON | POLYMERIZED HOT-MIX ASPHALT BINDER COURSE, IL-19.0, N70 | Base items | 886.000 | |||
40604152 | TON | POLYMERIZED HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "C", N70 | Base items | 532.000 | |||
42400100 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 4 INCH | Base items | 75.000 | |||
44000500 | FOOT | COMBINATION CURB AND GUTTER REMOVAL | Base items | 56.000 | |||
44000600 | SQ FT | SIDEWALK REMOVAL | Base items | 125.000 | |||
60235700 | EACH | INLETS, TYPE A, TYPE 3 FRAME AND GRATE | Base items | 1.000 | |||
60605000 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.24 | Base items | 60.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70100450 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 | Base items | 1.000 | |||
X0320050 | L SUM | CONSTRUCTION LAYOUT (SPECIAL) | Base items | 1.000 | |||
X4400196 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL (SPECIAL) | Base items | 5,748.000 | |||
X6030310 | EACH | FRAMES AND LIDS TO BE ADJUSTED (SPECIAL) | Base items | 3.000 | |||
No More Pay Items |