Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 6 | 7.00 | 0.00 | 3170096TBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
SPI 4755 | Abraham Lincoln Capital | Springfield Airport Authority | Springfield |
Contract Specifics |
---|
A voluntary pre-bid meeting will be held on Monday, October 19, 2020 at 01:30 PM in the Abraham Lincoln Capital Airport, Old Prairie Analytical Lab on 2nd floor. at 1200 Capital Airport Drive, Springfield, IL. Location Notes - Use Entrance for Springfield Airport Authority Administrative Offices. Meeting Description - For engineering information, contact Wes Ioerger, P.E. of Crawford, Murphy and Tilly, Inc., at (217) 572-1107. |
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
120 Calendar Days |
Previously advertised on July 31, 2020 (Item 04A). |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR106910 | EACH | REMOVE LIGHT FIXTURE | Base items | 27.000 | |||
AR106930 | EACH | REPLACE LIGHT FIXTURE | Base items | 27.000 | |||
AR108108 | FOOT | 1/C #8 5 KV UG CABLE | Base items | 750.000 | |||
AR108158 | FOOT | 1/C #8 5 KV UG CABLE IN UD | Base items | 3,000.000 | |||
AR108258 | FOOT | 2/C #8 5 KV UG CABLE IN UD | Base items | 250.000 | |||
AR108706 | FOOT | 1/C #6 COUNTERPOISE | Base items | 4,000.000 | |||
AR110501 | FOOT | 1-WAY CONC. ENCASED DUCT | Base items | 20.000 | |||
AR110504 | FOOT | 4-WAY CONCRETE ENCASED DUCT | Base items | 80.000 | |||
AR125100 | EACH | ELEVATED RETROREFLECTIVE MARKER | Base items | 26.000 | |||
AR125416 | EACH | MITL-BASE MOUNTED-LED | Base items | 24.000 | |||
AR125442 | EACH | TAXI GUIDANCE SIGN, 2 CHARACTER | Base items | 2.000 | |||
AR125444 | EACH | TAXI GUIDANCE SIGN, 4 CHARACTER | Base items | 6.000 | |||
AR125445 | EACH | TAXI GUIDANCE SIGN, 5 CHARACTER | Base items | 3.000 | |||
AR125470 | EACH | MODIFY EXISTING SIGN PANEL | Base items | 4.000 | |||
AR125515 | EACH | HIRL, BASE MOUNTED | Base items | 2.000 | |||
AR125525 | EACH | HIRL, INPAVEMENT | Base items | 1.000 | |||
AR125565 | EACH | SPLICE CAN | Base items | 2.000 | |||
AR125901 | EACH | REMOVE STAKE MOUNTED LIGHT | Base items | 33.000 | |||
AR125902 | EACH | REMOVE BASE MOUNTED LIGHT | Base items | 95.000 | |||
AR125904 | EACH | REMOVE TAXI GUIDANCE SIGN | Base items | 56.000 | |||
AR125905 | EACH | REMOVE RWY DISTANCE REMAIN SIGN | Base items | 8.000 | |||
AR125906 | EACH | REMOVE SPLICE CAN | Base items | 3.000 | |||
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 7,330.000 | |||
AR152621 | CU YD | REMOVE CONCRETE | Base items | 2.000 | |||
AR154506 | SQ YD | GRANULAR SUBBASE - 6" | Base items | 4,000.000 | |||
AR156520 | EACH | INLET PROTECTION | Base items | 6.000 | |||
AR156530 | ACRE | TEMPORARY SEEDING | Base items | 1.000 | |||
AR401610 | TON | BITUMINOUS SURFACE COURSE | Base items | 600.000 | |||
AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 900.000 | |||
AR501527 | S.Y. | 17.5" PCC PAVEMENT | Base items | 3,800.000 | |||
AR501905 | SQ YD | REMOVE PAVEMENT | Base items | 15,350.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 6,210.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 15,800.000 | |||
AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 3,350.000 | |||
AR620900 | SQ FT | PAVEMENT MARKING REMOVAL | Base items | 14,600.000 | |||
AR701512 | FOOT | 12" RCP, CLASS IV | Base items | 350.000 | |||
AR701515 | FOOT | 15" RCP, CLASS IV | Base items | 225.000 | |||
AR701518 | FOOT | 18" RCP, CLASS IV | Base items | 190.000 | |||
AR701900 | FOOT | REMOVE PIPE | Base items | 25.000 | |||
AR705524 | FOOT | 4" PERFORATED UNDERDRAIN W/SOCK | Base items | 1,125.000 | |||
AR705544 | FOOT | 4" NON PERFORATED UNDERDRAIN | Base items | 130.000 | |||
AR705635 | EACH | UNDERDRAIN COLLECTION STRUCTURE | Base items | 2.000 | |||
AR705640 | EACH | UNDERDRAIN CLEANOUT | Base items | 4.000 | |||
AR705645 | EACH | UNDERDRAIN CONNECTION | Base items | 2.000 | |||
AR751410 | EACH | INLET | Base items | 4.000 | |||
AR751530 | EACH | MANHOLE | Base items | 2.000 | |||
AR751900 | EACH | REMOVE INLET | Base items | 1.000 | |||
AR751940 | EACH | ADJUST INLET | Base items | 1.000 | |||
AR800308 | EACH | EXPLORATORY EXCAVATION | Base items | 2.000 | |||
AR800337 | C.Y. | UNCLASSIFIED EXCAVATION (NIGHT WORK) | Base items | 1,980.000 | |||
AR800346 | S.Y. | REMOVE PAVEMENT (NIGHT WORK) | Base items | 4,240.000 | |||
AR901510 | ACRE | SEEDING | Base items | 8.700 | |||
AR904510 | SQ YD | SODDING | Base items | 1,370.000 | |||
AR908515 | ACRE | HEAVY-DUTY HYDRAULIC MULCH | Base items | 8.700 | |||
AS152410 | CU YD | UNCLASSIFIED EXCAVATION | Additive 1 | 340.000 | |||
AS156520 | EACH | INLET PROTECTION | Additive 1 | 5.000 | |||
AS501905 | SQ YD | REMOVE PAVEMENT | Additive 1 | 11,175.000 | |||
AS901510 | ACRE | SEEDING | Additive 1 | 3.500 | |||
AS908515 | ACRE | HEAVY-DUTY HYDRAULIC MULCH | Additive 1 | 3.500 | |||
No More Pay Items |