Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
2 | 3 | 4.00 | 0.00 | KAQS(977) |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
35 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 97.000 | |||
40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 3.000 | |||
40800050 | TON | INCIDENTAL HOT-MIX ASPHALT SURFACING | Base items | 1.000 | |||
42300200 | SQ YD | PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, 6 INCH | Base items | 725.000 | |||
42400100 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 4 INCH | Base items | 16,561.000 | |||
42400800 | SQ FT | DETECTABLE WARNINGS | Base items | 237.000 | |||
44000200 | SQ YD | DRIVEWAY PAVEMENT REMOVAL | Base items | 703.000 | |||
44000500 | FOOT | COMBINATION CURB AND GUTTER REMOVAL | Base items | 254.000 | |||
44000600 | SQ FT | SIDEWALK REMOVAL | Base items | 3,160.000 | |||
60255500 | EACH | MANHOLES TO BE ADJUSTED | Base items | 3.000 | |||
60255700 | EACH | MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, OPEN LID | Base items | 1.000 | |||
60260300 | EACH | INLETS TO BE ADJUSTED WITH NEW TYPE 1 FRAME, OPEN LID | Base items | 5.000 | |||
60604400 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.18 | Base items | 254.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70102620 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701501 | Base items | 1.000 | |||
70102640 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701801 | Base items | 1.000 | |||
78001130 | FOOT | PAINT PAVEMENT MARKING - LINE 6" | Base items | 398.000 | |||
X0327618 | L SUM | LANDSCAPING (SPECIAL) | Base items | 1.000 | |||
No More Pay Items |