Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 7 | 0.00 | 0.00 | 4UN2(323) |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
25 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 725.000 | |||
20400800 | CU YD | FURNISHED EXCAVATION | Base items | 2,525.000 | |||
20700110 | TON | POROUS GRANULAR EMBANKMENT | Base items | 382.000 | |||
28000250 | POUND | TEMPORARY EROSION CONTROL SEEDING | Base items | 150.000 | |||
28000305 | FOOT | TEMPORARY DITCH CHECKS | Base items | 80.000 | |||
28000500 | EACH | INLET AND PIPE PROTECTION | Base items | 5.000 | |||
35100100 | TON | AGGREGATE BASE COURSE, TYPE A | Base items | 1,377.000 | |||
54213663 | EACH | PRECAST REINFORCED CONCRETE FLARED END SECTIONS 18" | Base items | 2.000 | |||
54213693 | EACH | PRECAST REINFORCED CONCRETE FLARED END SECTIONS 48" | Base items | 6.000 | |||
542A0223 | FOOT | PIPE CULVERTS, CLASS A, TYPE 1 18" | Base items | 36.000 | |||
542A0253 | FOOT | PIPE CULVERTS, CLASS A, TYPE 1 48" | Base items | 120.000 | |||
542D0220 | FOOT | PIPE CULVERTS, CLASS D, TYPE 1 15" | Base items | 60.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
LR355210 | TON | BITUMINOUS MATERIALS (PRIME COAT) | Base items | 5.000 | |||
LR403400 | TON | BITUMINOUS MATERIALS (COVER AND SEAL COATS) | Base items | 10.000 | |||
LR403500 | TON | COVER COAT AGGREGATE | Base items | 67.000 | |||
LR403600 | TON | SEAL COAT AGGREGATE | Base items | 33.000 | |||
X2501000 | ACRE | SEEDING, CLASS 2 (SPECIAL) | Base items | 0.750 | |||
X2810208 | TON | STONE RIPRAP, CLASS A4 (SPECIAL) | Base items | 139.000 | |||
X7011800 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD BLR 21 | Base items | 1.000 | |||
No More Pay Items |