Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
5 | 8 | 8.00 | 0.00 | N/A |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
SLO 4622 | Salem-Leckrone | Salem Airport Authority | Salem |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 60 days after the scheduled letting. |
31 Calendar Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150540 | L SUM | HAUL ROUTE | Base items | 1.000 | |||
AR152411 | L SUM | UNCLASSIFIED EXCAVATION | Base items | 1.000 | |||
AR152480 | SQ YD | SHOULDER ADJUSTMENT | Base items | 530.000 | |||
AR162216 | EACH | CLASS E MANUAL SLIDE GATE-16' | Base items | 1.000 | |||
AR162905 | EACH | REMOVE GATE | Base items | 1.000 | |||
AR201661 | FOOT | CLEAN & SEAL BITUMINOUS CRACKS | Base items | 1,000.000 | |||
AR209510 | TON | CRUSHED AGGREGATE BASE COURSE | Base items | 87.000 | |||
AR401613 | TON | BIT. SURF. CSE.-METHOD I, SUPERPAVE | Base items | 361.000 | |||
AR401655 | SQ YD | BUTT JOINT CONSTRUCTION | Base items | 573.000 | |||
AR602510 | GALLON | BITUMINOUS PRIME COAT | Base items | 85.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 434.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 151.000 | |||
AR701212 | FOOT | 12" CMP | Base items | 48.000 | |||
AR701900 | FOOT | REMOVE PIPE | Base items | 44.000 | |||
AR800571 | EACH | PAVEMENT MARKING-SPEC., HAND. SYM. | Base items | 1.000 | |||
AS162761 | EACH | ELECTRIC GATE UPGRADE | Additive 1 | 1.000 | |||
No More Pay Items |