Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 7 | 0.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
75 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20201200 | CU YD | REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL | Base items | 10.000 | |||
20400800 | CU YD | FURNISHED EXCAVATION | Base items | 947.000 | |||
30200650 | SQ YD | PROCESSING MODIFIED SOIL 12" | Base items | 12,431.000 | |||
30201250 | SQ YD | PROCESSING MODIFIED SOIL 24" | Base items | 4,608.000 | |||
30201500 | TON | LIME | Base items | 531.000 | |||
42000501 | SQ YD | PORTLAND CEMENT CONCRETE PAVEMENT 10" (JOINTED) | Base items | 17,039.000 | |||
42400100 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 4 INCH | Base items | 4,882.000 | |||
42400300 | SQ FT | PORTLAND CEMENT CONCRETE SIDEWALK 6 INCH | Base items | 1,152.000 | |||
44000100 | SQ YD | PAVEMENT REMOVAL | Base items | 17,039.000 | |||
44000500 | FOOT | COMBINATION CURB AND GUTTER REMOVAL | Base items | 298.000 | |||
44000600 | SQ FT | SIDEWALK REMOVAL | Base items | 3,078.000 | |||
44213204 | EACH | TIE BARS 3/4" | Base items | 1,782.000 | |||
60608600 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE M-6.06 | Base items | 298.000 | |||
67000400 | CAL MO | ENGINEER'S FIELD OFFICE, TYPE A | Base items | 6.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70100820 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701451 | Base items | 1.000 | |||
78009000 | SQ FT | MODIFIED URETHANE PAVEMENT MARKING - LETTERS AND SYMBOLS | Base items | 19.000 | |||
78009004 | FOOT | MODIFIED URETHANE PAVEMENT MARKING - LINE 4" | Base items | 7,502.000 | |||
X0326864 | SQ FT | BRICK SIDEWALK REMOVAL | Base items | 1,314.000 | |||
X0327008 | EACH | REMOVE AND RELOCATE SIGN (SPECIAL) | Base items | 4.000 | |||
X7301035 | FOOT | SIGN POST - SERIES 218 | Base items | 36.000 | |||
X7830060 | SQ FT | GROOVING FOR RECESSED PAVEMENT MARKING, LETTERS AND SYMBOLS | Base items | 19.000 | |||
X7830070 | FOOT | GROOVING FOR RECESSED PAVEMENT MARKING 5" | Base items | 7,502.000 | |||
No More Pay Items |