Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
2 | 2 | 8.00 | 0.00 | 317SBGPTBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
EZI 4710 | Kewanee Municipal | Kewanee Airport Authority | Kewanee |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
40 Calendar Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150530 | L SUM | TRAFFIC MAINTENANCE | Base items | 1.000 | |||
AR150540 | L SUM | HAUL ROUTE | Base items | 1.000 | |||
AR152480 | SQ YD | SHOULDER ADJUSTMENT | Base items | 3,864.000 | |||
AR156510 | FOOT | SILT FENCE | Base items | 168.000 | |||
AR201661 | FOOT | CLEAN & SEAL BITUMINOUS CRACKS | Base items | 4,707.000 | |||
AR201663 | FOOT | SAND MIX CRACK REPAIR | Base items | 638.000 | |||
AR201670 | SQ YD | CRACK CONTROL FABRIC | Base items | 7,787.000 | |||
AR401613 | TON | BIT. SURF. CSE.-METHOD I, SUPERPAVE | Base items | 955.000 | |||
AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 7,787.000 | |||
AR401660 | FOOT | SAW & SEAL BIT. JOINTS | Base items | 510.000 | |||
AR401665 | FOOT | BITUMINOUS PAVEMENT SAWING | Base items | 1,170.000 | |||
AR401910 | SQ YD | REMOVE & REPLACE BIT. PAVEMENT | Base items | 147.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 1,870.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 3,178.000 | |||
AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 3,400.000 | |||
AR901510 | ACRE | SEEDING | Base items | 0.800 | |||
AR908510 | ACRE | MULCHING | Base items | 0.800 | |||
No More Pay Items |