Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
2 | 2 | 0.00 | 0.00 | 317SBGPTBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
C73 4876 | Dixon Municipal | City of Dixon | Dixon |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
75 Calendar Days |
This project is currently unfunded, but actively seeking discretionary funds. |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR108158 | FOOT | 1/C #8 5 KV UG CABLE IN UD | Base items | 27,450.000 | |||
AR109210 | L SUM | VAULT MODIFICATIONS | Base items | 1.000 | |||
AR109321 | EACH | 10 KW REGULATOR, STYLE 1 | Base items | 2.000 | |||
AR110014 | FOOT | 4" DIRECTIONAL BORE | Base items | 500.000 | |||
AR115610 | EACH | ELECTRICAL HANDHOLE | Base items | 1.000 | |||
AR125106 | EACH | RELOC. ELEV. RETROREFLECTIVE MARKER | Base items | 8.000 | |||
AR125411 | EACH | MITL-STAKE MOUNTED-LED | Base items | 212.000 | |||
AR125416 | EACH | MITL-BASE MOUNTED-LED | Base items | 34.000 | |||
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR800164 | EACH | REMOVE RETROREFLECTIVE MARKER | Base items | 197.000 | |||
No More Pay Items |