Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 6 | 10.00 | 0.00 | 317SBGPTBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
3LF 4819 | Litchfield Municipal | Litchfield Airport Authority | Litchfield |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
100 Calendar Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR108158 | FOOT | 1/C #8 5 KV UG CABLE IN UD | Base items | 4,753.000 | |||
AR110503 | FOOT | 3-WAY CONCRETE ENCASED DUCT | Base items | 60.000 | |||
AR115610 | EACH | ELECTRICAL HANDHOLE | Base items | 2.000 | |||
AR125410 | EACH | MITL-STAKE MOUNTED | Base items | 33.000 | |||
AR125415 | EACH | MITL-BASE MOUNTED | Base items | 10.000 | |||
AR125443 | EACH | TAXI GUIDANCE SIGN, 3 CHARACTER | Base items | 2.000 | |||
AR125921 | EACH | REPLACE STAKE MOUNTED LIGHT | Base items | 33.000 | |||
AR125922 | EACH | REPLACE BASE MOUNTED LIGHT | Base items | 5.000 | |||
AR125932 | EACH | REPLACE SIGN PANEL | Base items | 4.000 | |||
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150540 | L SUM | HAUL ROUTE | Base items | 1.000 | |||
AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 4,069.000 | |||
AR154604 | SQ YD | GRANULAR DRAINAGE SUBBASE - 4" | Base items | 7,730.000 | |||
AR155540 | TON | BY-PRODUCT LIME | Base items | 200.000 | |||
AR155612 | S.Y. | SOIL PROCESSING-12" | Base items | 8,130.000 | |||
AR156510 | FOOT | SILT FENCE | Base items | 200.000 | |||
AR156513 | SQ YD | SEPARATION FABRIC | Base items | 7,730.000 | |||
AR156520 | EACH | INLET PROTECTION | Base items | 6.000 | |||
AR156530 | ACRE | TEMPORARY SEEDING | Base items | 12.000 | |||
AR156531 | SQ YD | EROSION CONTROL BLANKET | Base items | 650.000 | |||
AR156543 | SQ YD | RIPRAP-GRADATION NO. 3 | Base items | 105.000 | |||
AR209606 | SQ YD | CRUSHED AGG. BASE COURSE - 6" | Base items | 7,730.000 | |||
AR401613 | TON | BIT. SURF. CSE.-METHOD I, SUPERPAVE | Base items | 950.000 | |||
AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 465.000 | |||
AR401663 | FOOT | LONGITUDINAL JOINT SEALANT | Base items | 2,000.000 | |||
AR401900 | SQ YD | REMOVE BITUMINOUS PAVEMENT | Base items | 470.000 | |||
AR401910 | SQ YD | REMOVE & REPLACE BIT. PAVEMENT | Base items | 66.000 | |||
AR403613 | TON | BIT. BASE CSE.-METHOD I, SUPERPAVE | Base items | 950.000 | |||
AR602510 | GALLON | BITUMINOUS PRIME COAT | Base items | 2,200.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 1,250.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 2,308.000 | |||
AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 2,380.000 | |||
AR620900 | SQ FT | PAVEMENT MARKING REMOVAL | Base items | 220.000 | |||
AR701230 | FOOT | 30" CMP | Base items | 25.000 | |||
AR701713 | L.F. | RCEP SPAN 30 RISE 19 | Base items | 88.000 | |||
AR705506 | FOOT | 6" PERFORATED UNDERDRAIN | Base items | 3,800.000 | |||
AR705546 | FOOT | 6" NON PERFORATED UNDERDRAIN | Base items | 225.000 | |||
AR705610 | EACH | CONCRETE HEADWALL FOR UNDERDRAIN | Base items | 2.000 | |||
AR705635 | EACH | UNDERDRAIN COLLECTION STRUCTURE | Base items | 4.000 | |||
AR705640 | EACH | UNDERDRAIN CLEANOUT | Base items | 10.000 | |||
AR752418 | EACH | PRECAST REINFORCED CONC. FES 18" | Base items | 4.000 | |||
AR752724 | EACH | P R CONC. FES EQ. ROUND SIZE 24" | Base items | 2.000 | |||
AR800476 | L SUM | REMOVE AIRFIELD LIGHTING | Base items | 1.000 | |||
AR800564 | L SUM | CABLE & CCR TESTING & CALIBRATION | Base items | 1.000 | |||
AR800567 | L.F. | FILL PIPE WITH CLSM | Base items | 210.000 | |||
AR800568 | L.F. | 16" HDPE PIPE | Base items | 305.000 | |||
AR800569 | L.F. | 18" HDPE PIPE | Base items | 250.000 | |||
AR901510 | ACRE | SEEDING | Base items | 12.000 | |||
AR908510 | ACRE | MULCHING | Base items | 12.000 | |||
No More Pay Items |