Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 5 | 7.00 | 0.00 | 317SBGPTBD |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
DNV 4742 | Vermilion Regional | Vermilion Regional Airport Authority | Danville |
Contract Specifics |
---|
A voluntary pre-bid meeting will be held on Thursday, June 2, 2022 at 01:00 PM in the Vermilion Regional Airport Authority at 22633 N Bowman Ave Ste 1, Danville, IL 61834. Location Notes - In the Administration Office. Meeting Description - For engineering information, contact Eric Hills, P.E. of Crawford, Murphy and Tilly, Inc. at (217) 572-1150. |
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
123 Calendar Days |
Previously advertised on July 30, 2021 (Item 03A). |
This project is currently unfunded but actively seeking discretionary funds |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR106910 | EACH | REMOVE LIGHT FIXTURE | Base items | 15.000 | |||
AR108108 | FOOT | 1/C #8 5 KV UG CABLE | Base items | 80.000 | |||
AR108158 | FOOT | 1/C #8 5 KV UG CABLE IN UD | Base items | 6,420.000 | |||
AR108208 | FOOT | 2/C #8 5 KV UG CABLE | Base items | 100.000 | |||
AR108258 | FOOT | 2/C #8 5 KV UG CABLE IN UD | Base items | 660.000 | |||
AR108706 | FOOT | 1/C #6 COUNTERPOISE | Base items | 6,120.000 | |||
AR108960 | FOOT | REMOVE CABLE | Base items | 5,670.000 | |||
AR110102 | EACH | DUCT MARKER - IN PAVEMENT | Base items | 2.000 | |||
AR110504 | FOOT | 4-WAY CONCRETE ENCASED DUCT | Base items | 75.000 | |||
AR125100 | EACH | ELEVATED RETROREFLECTIVE MARKER | Base items | 7.000 | |||
AR125410 | EACH | MITL-STAKE MOUNTED | Base items | 53.000 | |||
AR125415 | EACH | MITL-BASE MOUNTED | Base items | 16.000 | |||
AR125442 | EACH | TAXI GUIDANCE SIGN, 2 CHARACTER | Base items | 1.000 | |||
AR125443 | EACH | TAXI GUIDANCE SIGN, 3 CHARACTER | Base items | 2.000 | |||
AR125444 | EACH | TAXI GUIDANCE SIGN, 4 CHARACTER | Base items | 1.000 | |||
AR125446 | EACH | TAXI GUIDANCE SIGN, 6 CHARACTER | Base items | 1.000 | |||
AR125904 | EACH | REMOVE TAXI GUIDANCE SIGN | Base items | 7.000 | |||
AR125913 | EACH | REMOVE EDGE LIGHT | Base items | 83.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 12,300.000 | |||
AR152490 | CU YD | CRUSHED AGGREGATE BACKFILL | Base items | 600.000 | |||
AR152515 | CU YD | SUBGRADE UNDERCUT | Base items | 1,200.000 | |||
AR156510 | FOOT | SILT FENCE | Base items | 600.000 | |||
AR156513 | SQ YD | SEPARATION FABRIC | Base items | 1,150.000 | |||
AR156515 | FOOT | STRAW WATTLE | Base items | 60.000 | |||
AR156520 | EACH | INLET PROTECTION | Base items | 3.000 | |||
AR209607 | SQ YD | CRUSHED AGG. BASE COURSE - 7" | Base items | 11,230.000 | |||
AR401610 | TON | BITUMINOUS SURFACE COURSE | Base items | 1,540.000 | |||
AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 1,100.000 | |||
AR401655 | SQ YD | BUTT JOINT CONSTRUCTION | Base items | 255.000 | |||
AR401921 | SQ YD | REMOVE PAVEMENT | Base items | 9,900.000 | |||
AR403610 | TON | BITUMINOUS BASE COURSE | Base items | 3,285.000 | |||
AR403630 | EACH | BITUMINOUS BASE TEST SECTION | Base items | 1.000 | |||
AR602510 | GALLON | BITUMINOUS PRIME COAT | Base items | 3,430.000 | |||
AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 2,940.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 3,900.000 | |||
AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 4,960.000 | |||
AR620900 | SQ FT | PAVEMENT MARKING REMOVAL | Base items | 1,370.000 | |||
AR701524 | FOOT | 24" RCP, CLASS IV | Base items | 10.000 | |||
AR701900 | FOOT | REMOVE PIPE | Base items | 10.000 | |||
AR705524 | FOOT | 4" PERFORATED UNDERDRAIN W/SOCK | Base items | 3,945.000 | |||
AR705544 | FOOT | 4" NON PERFORATED UNDERDRAIN | Base items | 285.000 | |||
AR705635 | EACH | UNDERDRAIN COLLECTION STRUCTURE | Base items | 2.000 | |||
AR705640 | EACH | UNDERDRAIN CLEANOUT | Base items | 11.000 | |||
AR705645 | EACH | UNDERDRAIN CONNECTION | Base items | 2.000 | |||
AR705904 | EACH | REMOVE UNDERDRAIN CLEANOUT | Base items | 3.000 | |||
AR751411 | EACH | INLET-TYPE A | Base items | 1.000 | |||
AR751900 | EACH | REMOVE INLET | Base items | 1.000 | |||
AR901510 | ACRE | SEEDING | Base items | 11.000 | |||
AR904510 | SQ YD | SODDING | Base items | 1,710.000 | |||
AR905520 | CU YD | TOPSOILING (FROM OFF SITE) | Base items | 2,400.000 | |||
AR908514 | ACRE | LIGHT-DUTY HYDRAULIC MULCH | Base items | 11.000 | |||
No More Pay Items |