March 05, 2021 Letting 12:00 PM
038-76N77

Bulletin Description

4.1 miles of crack and joint sealing on IL 159 from 0.1 miles north of Fountains Parkway to Rosewood Village Drive.
Region District DBE % VBP % Federal Project #
5 8 15.00 0.00 NHPPPET2(318)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • St. Clair
  • FAP 600
  • (130-1,130-2)CJS-1
  • C-98-034-21
  • 8-00802-0000
Contract Specifics
15 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 2 Answered ) Questions not accepted as of February 23, 2021 04:30 PM.

  • Since this is a moving operation urban project will ROAD CONSTRUCTION AHEAD signs be required on every side road through this project?
    ROAD CONSTRUCTION AHEAD signs will not be required for the moving operation at side roads when flaggers are present. (02/23/2021)

  • The first paragraph in the special provisions under Traffic Control and Protection Special, state that the signs shall be dual indicated. This would put the signs on the left side in the bidirectional left turn lane. Please clarify what the the intent is with these signs as there is no median to place signs.
    The intent of paragraph 3 in TRAFFIC CONTROL AND PROTECTION, (SPECIAL) is to require additional ROAD CONSTRUCTION AHEAD AND LANE CLOSED AHEAD signs on the right shoulders for both bounds when working in the bi-directional turn lanes. Signs should not be placed in the bi-directional turn lanes. (02/23/2021)

Authorized Bidders

  • 1175 Complete Asphalt Service Co.
    1601 Kamar Drive
    Pittsfield, IL 62363
    PO Box 457
    Pittsfield, IL 62363
    Phone: (217) 285-6099 Fax: (217) 285-6094 Email: casco3@frontier.com
    $164,554.57

  • 1443 Denler, Inc.
    20502 S Cherry Hill Rd
    Joliet, IL 60433
    Phone: (708) 479-5005 Fax: (708) 479-5015 Email: info@denlerinc.com

  • 1882 Freehill Asphalt, Inc.
    103 Yount Ave
    Watseka, IL 60970
    PO Box 154
    Watseka, IL 60970
    Phone: (815) 432-5438 Fax: (815) 432-5439 Email: thomasfreehill@sbcglobal.net

  • 2708 HSC Pavement Maintenance
    896 Funkhouser Street
    Albion, IL 62806
    Phone: No Record Fax: No Record Email: No Record

  • 3163 Kinney Contractors, Inc.
    19342 E. Frontage Rd.
    Raymond, IL 62560
    Phone: (217) 229-3322 Fax: (217) 229-3609 Email: kinney@roadbuilder.net
    $224,940.07

  • 5289 SKC Construction, Inc.
    695 Church Road
    Elgin, IL 60123
    P.O. Box 503
    West Dundee, IL 60118
    Phone: (847) 214-9800 Fax: (847) 214-9041 Email: ttabor@skcconstruction.net

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
45100100 FOOT CRACK ROUTING (PAVEMENT) Base items 147,677.000
45100200 POUND CRACK FILLING Base items 59,071.000
67100100 L SUM MOBILIZATION Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 28.000
70200100 L SUM NIGHTTIME WORK ZONE LIGHTING Base items 1.000
X7010216 L SUM TRAFFIC CONTROL AND PROTECTION, (SPECIAL) Base items 1.000
Z0076600 HOUR TRAINEES Base items 500.000 $0.80
Z0076604 HOUR TRAINEES TRAINING PROGRAM GRADUATE Base items 500.000 $15.00
No More Pay Items