Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 4 | 2.00 | 0.00 | 317SBGP133/139 |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
MQB 4400 | Macomb Municipal | Macomb Airport Authority | Macomb |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 60 days after the scheduled letting. |
28 Calendar Days |
Previously advertised on April 27, 2018 (Item 01A). |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR108656 | FOOT | 3/C #6 600 V UG CABLE IN UD | Base items | 5,515.000 | |||
AR110014 | FOOT | 4" DIRECTIONAL BORE | Base items | 80.000 | |||
AR125565 | EACH | SPLICE CAN | Base items | 1.000 | |||
AR125615 | EACH | PAPI (L-880 SYSTEM) | Base items | 2.000 | |||
AR125909 | EACH | REMOVE VASI | Base items | 2.000 | |||
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR152442 | CU YD | OFFSITE BORROW EXCAVATION | Base items | 60.000 | |||
AR156511 | EACH | DITCH CHECK | Base items | 1.000 | |||
AR156531 | SQ YD | EROSION CONTROL BLANKET | Base items | 200.000 | |||
AR701521 | FOOT | 21" RCP, CLASS IV | Base items | 48.000 | |||
AR752421 | EACH | PRECAST REINFORCED CONC. FES 21" | Base items | 4.000 | |||
AR901510 | ACRE | SEEDING | Base items | 0.100 | |||
No More Pay Items |